delay of delivery of possession and in deficient and
incomplete construction work, more so when the Complainant consumer fulfilled
his commitments and obligations under ... delivery of possession of the premises
and for defective and incomplete construction work within 30 days from receipt
of this order, failing which the amount
complainant and started construction work, but the construction work was delayed by 6 months due to funds crunch, and also flat nominee was not available ... agreement, and started construction work, but the opposite party could not complete the construction, and he abandoned the work.
7. The opposite party agreed
pleaded that Opponent No.2 left the construction work incomplete and
went away and thereafter, cancelled the purchase agreement. Opponent No.3 is the owner ... Opponent No.2 constructed 40% of the
building and 30% work was left incomplete because he had not received monies
from the Complainant. All other
raised multiple grievances before the Opposite Parties regarding incomplete
construction work, non-provision of amenities, and serious functional deficiencies prior
to the proposed handover scheduled ... provide the same and had handed over
incomplete work with several deficiencies. It was stated that the construction quality was
substandard with continuous seepage
2009, Shri Sanjay Putalaji Darekar & Ors.
V/s. M/s.Siddhi Construction Co. through its partner and Ors., by Addl.
District Consumer Disputes Redressal ... allowed and it was
directed that the builder shall complete the incomplete construction work,
provide all the amenities as mentioned in para
features (such as compound wall, gate,
ramp, and other specifications), and incomplete construction
work. Despite repeated written communications by the
DISMISSED PAGE ... Complainants highlighting major defects and pending works--
such as cracked terrace, damaged fittings, incomplete finishing,
structural issues, and deviation from agreed specifications--the
Opposite Parties
costs of Rs.3,20,000/-, to pay cost of
construction of incomplete work amounting to Rs.2 lakhs. The
complainants have also claimed compensation ... present market
valuation along with escalation costs, cost of incomplete work and
compensation of Rs.5 lakhs.
According to complainants they are law abiding citizens
time of
taking entire amount of consideration the construction work was
incomplete, which is still not completed. Instead of executing
'agreement to sale ... loan amount from opponent
no.9 and 10, though the construction work was incomplete and
8 CC/7/2018
was just started. Opponent
further completed the work with the help of architect.
Complainant started incomplete construction work of their flat No.601. Learned
advocate for the complainant draws ... incomplete work which was shown to the op. but Opposite party
avoided to complete the same. Therefore the Complainant get started the work
bill in
respect of cost of tiles , POP work, extra electric work, modular kitchen work,
work for removing tiles and photographs etc. with the written ... alleged incomplete construction work of flat no. 202, there is variation in pleading in the complaint and
commissioner report.
iii) Extra
work allegedly done