amount of `11,02,186/-
towards instalment against commencement of internal plastering and the demand
is not in accordance with clause ... Agreement of Sale which
stipulates payment of instalment against commencement of internal plaster is `10,71,225/-.
5. The
opposite party caused considerable delay
roof
373500
On start of brick work
461100
On start of internal plastering
760100
On start of flooring
635600
On start of internal electrification ... payment plan extracted above, the company should have completed the internal plaster work of the unit and also more than 90% of the flooring work
Annexure C-5) which was due on the start of internal plaster. Since the Opposite Party No.1 had not even started the internal plaster ... plaster. However, as per the case of the Complainant, though no internal plaster was started in the apartment, yet the Opposite Party No.1 continued
construction was delayed and had not reached the
stage of internal plaster, fixtures of doors and windows etc..
Accordingly, the Ops were asked to complete ... completion of Door 20% of Basic 875350
Window Frames
Fixing/Internal Plastering,
within 180 days from the date
of booking, whichever is later
same.
ii. There are cracks to the internal plaster of his flat. That the
opponent builder had not done proper curring of the plaster ... grounds
that the opponent builder failed to form the society, the internal
plaster had developed cracks due to insufficient curring. Possession
of flat was given
completion of doors and windows frames
and internal plastering
24.06.2011
6,40,000.00
C-13 (as per statement)
7
At the time of offer
start of Top Floor Roof Slab
6% On start of Internal Plaster
5% At the time of offer of possession
5. On a visit
there are no internal electricity fittings, no internal plumbing work done, rather there is incomplete work of external plastering, walls and flooring. It was further ... completion of internal electrification
5% of BSP
On completion of internal plumbing
5% of BSP
On completion of external plastering
5% of BSP
On final
demand for an amount of `4,15,800/- on completion of
internal plaster and an additional amount of `3,11,850/- for completion of
external ... 2006 had demanded the
amount for completion of brick-work, internal plaster, external plaster and
the interest on the delayed payment alongwith a statement
Shukla on 10.1.2019. On 28.2.2019 demand due for the stage on internal plaster and flooring for Rs.92,892.00 (including previous dues) was raised ... complainant on 28.02.2019 to demand due for the states on internal plaster and flooring for Rs.92,892/- and this demand was made not paid