Irb Infrastructure Developers ... vs The Hyderabad Growth Corridor Limited on 11 November, 2025
HON'BLE SRI JUSTICE LAXMI NARAYANA ALISHETTY
WRIT PETITION No.44729
Toll Tax and ECC
collection from Sahakar Global Limited JV and IRB Infrastructure
Developers Limited or not?
202. What were the bid amount of both ... Whether the bid amount of second bidder Le. IRB Infrastructure
Developers Limited was less than the reserve price of the tender
document for toll
Toll Tax and ECC
collection from Sahakar Global Limited JV and IRB Infrastructure
Developers Limited or not?
202. What were the bid amount of both ... Whether the bid amount of second bidder Le. IRB Infrastructure
Developers Limited was less than the reserve price of the tender
document for toll
made by the learned Senior Advocate appearing for
the respondent, M/s. IRB Ahmedabad Vadodara Super Express Tollways
Pvt. Ltd. We must record that ... statement is also made by
the learned Senior Advocate appearing for IRB Infrastructure
Developers Limited.
It is clarified that the direction to erase the aforesaid
NHAI, pursuant to the Notice Inviting
Tenders28, were grant-based. IRB Infrastructure Developers Pvt Ltd29
was the successful bidder, and sought a financial grant from
work of construction and maintenance of
highway to its parent company, IRB Infrastructure
Developers Ltd which executes the work and discharges
the applicable GST Liability ... under GST,
GST charged by the EPC Contractor i.e. IRB Infrastructure
Developers Limited is reversed in respective month while
filing the GST returns. During
work of construction and maintenance of
highway to its parent company, IRB Infrastructure
Developers Ltd which executes the work and discharges
the applicable GST Liability ... under GST,
GST charged by the EPC Contractor i.e. IRB Infrastructure
Developers Limited is reversed in respective month while
filing the GST returns. During
another Award under which the parent company of the respondent,
namely, IRB Infrastructure Developers Ltd., is liable to pay
substantial amount to the petitioner, National ... respondent Yedeshi
Aurangabad Tollway Limited, to procure the documents from IRB
Infrastructure Developers Ltd. to furnish the said documents to the
learned counsel
Sanghatana .. Petitioner
Versus
Modern Road Makers Pvt. Ltd.
(A Subsidiary of IRB Infrastructure Developers
Ltd.) and Ors. .. Respondents
....................
Mr. A.S. Rao, Advocate for Petitioner
Marg, New Delhi.
(ii) It is alleged that one M/s IRB Infrastructure Developers Ltd was
declared to be the successful bidder