account with the said company are settled and he has some surplus
material supplied by the said company which is to be returned ... requesting the said
company for return of the surplus material. He stated that he had offered
several times to the said company for return
clarification as to how the milestone payments
against the surplus material handed over to BSNL shall be paid to the
Vendor, for which a specific ... clarification was sought as to how the milestone
payments against the surplus material handed over to BSNL shall be paid to
the Vendor
dispatch schedule for Tata Motors
Lucknow and stated that the excess materials would be available for ABB to
collect from Techno's site, commencing ... documents from other purchase
orders to validate the existence of surplus materials with Techno. Thus, the
Arbitrator's conclusions premised on this document
stripped surface by
manual or mechanical means, approaches, stacking/disposal
of surplus excavated material within a lead of 1km etc. 5,043,600
complete ... grade and
ramming/compacting the bottom, leveling, approaches,
stacking/disposal of surplus excavated material within a
lead of 1km etc. complete as per specification, drawing
that he had
removed all the scaffolding, surplus materials and rubbish
prior to 17.08.2015. He further confirmed that he had
received the payment in respect
requested them for
issuance of gate passes to remove the surplus material from the
site and thereafter, he sent another letter ... also
requested for issuance of the gate pass for removing the surplus
material, equipments etc. from the site.
17. The plaintiff further submit that
dated 07-02-2017. The plaintiff had not supplied any
above said material by that time or it had confirmed about
of their procurement ... stated T&P such as welding machine etc. and surplus
material lying at site, different groups of firm's worker
visited and returned
Shri Ajay Kalra vs Delhi Developement Authority on 20 December, 2023
Author: Neena Bansal Krishna
Tirunelveli District.
2.It is stated that the respondents had dumped excavated materials of the
project of excavation of Food Carrier Canal from Kannadian Channel ... project. The petitioner purchased the aforementioned land on
13.08.2021. Some dumped surplus salt materials still remain.
3.In the counter affidavit filed by the Executive
Tirunelveli District.
2. It is stated that the respondent had dumped excavated materials of the
project of excavation of Flood Carrier Canal from Kannadian channel ... project. The petitioner purchased the aforementioned land on
17.10.2020. Some dumped surplus salt material still remain.