Chandrakant Mahadev Kadam vs Asstt. Engineer, Mseb, Atpadi & Ors. on 29 September, 2003
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION ... State Commission, Maharashtra)
Chandrakant Mahadev Kadam Petitioner
Versus
Asstt. Engineer, MSEB, Atpadi & Ors. Respondents
BEFORE :
HON'BLE MR. JUSTICE D.P.WADHWA, PRESIDENT
Plastic in Dhule and had secured electricity supply of 130 HP from MSEB on 29.06.1996 and paid Rs.2,31,910 towards various charges ... machinery and company resolution authorizing a director to execute the application with MSEB. On 22.06.2000, after adjusting the refund amount, the Superintending Engineer required them
Petitioner
Versus
1. Executive Engineer,
Maharashtra State Electricity Distribution
Company Ltd. (Formerly MSEB),
Congress Nagar Division
Dhantoli, Nagpur- 440012
2. Asst. Engineer,
Maharashtra State Electricity ... Distribution
Company Ltd. (Formerly MSEB),
Trimurty Nagar Sub Division
Trimurty Nagar, Nagpur 440022
3. Junior Engineer,
Maharashtra State Electricity Distribution
Company Ltd. (Formerly MSEB),
Rana
GANESH PRASAD, 76, TULSHIBAGWALE COLONY, SAHAKARNAGAR NO. 2, PUNE-9 MAHARASHTRA 2. MSEB LTD. RASTA PETH THROUGH SUPERINTENDENT ENGINEER, MSEB LTD. RASTA PETH PUNE ... MAHARASHTRA 3. DY. EXECUTIVE ENGINEER MSEB LTD. SWARGATE, SUB DIVISION SWARGATE PUNE MAHARASHTRA 4. EXECUTIVE ENGINEER, MSEB LTD. PADMAVATI DIVISION, SANGAM SOCIETY PUNE-SATARA ROAD
flat purchasers were required to pay the
following charges:-
i)
MSEB Deposits and Cable laying charges.
ii)
Water Connection Deposits and meter
charges.
iii)
CIDCO ... strictly prove the same. Electric meter was provided
to the complainant through MSEB and was erected and was working well. The said
meter was transferred
loss was estimated at Rs 8.75 crores. The Maharashtra State Electricity Board (MSEB) opined the probable cause of the fire to be an electrical short ... accidental or that the Police prepared a panchnama or that the MSEB issued any certificate stating the probable cause of fire to be a short
share money, Rs.6000/- as security deposit, Rs.40000/-, as MSEB charges, Rs.2000/-, as legal charges, Rs.2000/- as society registration charges and maintenance ... 6000/- was taken as security against non-payment of maintenance charges. MSEB charges of Rs.40000/- was invested in installation of cables, 3 phase meter
share money, Rs.6000/- as security deposit, Rs.40000/-, as MSEB charges, Rs.2000/-, as legal charges, Rs.2000/- as society registration charges and maintenance ... 6000/- was taken as security against non-payment of maintenance charges. MSEB charges of Rs.40000/- was invested in installation of cables, 3 phase meter
share money, Rs.6000/- as security deposit, Rs.40000/-, as MSEB charges, Rs.2000/-, as legal charges, Rs.2000/- as society registration charges and maintenance ... 6000/- was taken as security against non-payment of maintenance charges. MSEB charges of Rs.40000/- was invested in installation of cables, 3 phase meter
Complainant.
3)
Rs.29960/- should be paid to the Complainant towards
outstanding MSEB Bills.
4)
Similarly Rs.33,363/- should be paid to the Complainant