MoEF&CC for approval of the standing committee of the NBWL and as per prevailing legal provisions the permission be obtained from ... forwarded to MoEF&CC for approval of standing committee of NBWL and following action may also be taken simultaneously:
(a) The social Impact assessment
such projects were to be examined by National Board of Wild Life (NBWL) and subject to the decision of NBWL and till the time ... clearance of NBWL is obtained, the concerned Authority was directed not to issue Completion Certificates to the Projects. These orders were passed during the construction
peen recommended in the NBWL’s draft
guideline document mentioned above (pages 8-
13, and 17-21). While fully endorsing these
recommended management measures ... activities are
within 10 Kms zone, be referred to Standing
Committee of NBWL.
2. Statutory Provisions
2.1 Section 5 C(1) of the Wildlife
(Protection
exhaustive set of management measures have
peen recommended in the NBWL’s draft
guideline document mentioned above (pages 8-
13, and 17-21). While fully ... activities are within 10 Kms
zone, be referred to Standing Committee of
NBWL.
2. Statutory Provisions
2.1 Section 5 C(1) of the Wildlife
____________
Page
held on 12.04.2010 that the Standing Committee of
National Board for Wildlife (NBWL) excluded the area falling on either
side of the road within ... that the recommendation dated 12.04.2010 of the Standing
Committee of NBWL was approved.
11. Clearly therefore, the project could not have been undertaken
before
second respondent has
issued notices informing the petitioners that unless they get NBWL
http://www.judis.nic.in
4
clearance certificate within a period
extent the issue of completion certificate was withheld till the clearance from NBWL could not have contributed to the delay in offering possession ... builder could obtain the completion certificate on the project being cleared by NBWL. If there was a delay on the part of the Government
Authority
(SEIAA).
vi) Permission was not obtained from the Standing
Committee of NBWL even though the project falls within
10 km of national park which ... 2004 requiring project proponents to seek clearance from
the Standing Committee of NBWL for projects falling within 10
km of national parks/sanctuaries
extent the issue of completion certificate was withheld till the clearance from NBWL could not have contributed to the delay in offering possession ... builder could obtain the completion certificate on the project being cleared by NBWL. If there was a delay on the part of the Government
extent the issue of completion certificate was withheld till the clearance from NBWL could not have contributed to the delay in offering possession ... builder could obtain the completion certificate on the project being cleared by NBWL. If there was a delay on the part of the Government