Jharkhand Urja Sancharan Nigam Ltd vs M/S Kohinoor Power Pvt. Ltd & Anr. Rpd & ... on 8 March, 2017

upon by the State Commission are reproduced below: "A4: GRID INTERCONNECTION/PARALLEL OPERATION 4.1 The CPP and dedicated transmission/distribution lines and substations shall ... necessary for ensuring integrated grid operations and for achieving the maximum safety, economy and efficiency in the operation of power system in the state
Appellate Tribunal For Electricity Cites 32 - Cited by 0 - Full Document