decides that POC is leviable for the CPPs operating in
parallel with the state grid. The charge decided in this order is
applicable ... shall apply to the new CPPs, operating in parallel with
State transmission utilities (Transmission Licensee) and/or distribution
licensee network in the grid."
Page
getting cross
subsidy surcharge which is higher than the parallel operation charges which was
being paid earlier. Once it is held that ... generating plant was not operating as a
captive generating plant then there was no liability to pay parallel operation charges.
16. Section 42 (2) deals
Tata Power Company Limited vs Maharashtra Electricity Regulatory ... on 21 December, 2012
Appeal No.132
Tarini Infrastructure Limited vs Gujarat Urja Vikas Nigam Ltd. & Ors on 31 May, 2012
M/S Maruti Suzuki India Ltd vs Haryana Electricity Regulatory ... on 4 October, 2012
Judgment
Brihanmumbai Electricity Supply And ... vs Maharashtra Electricity Regulatory ... on 4 April, 2012
Judgment in Appeal
Union Of India Through Southern Railway vs Tamil Nadu Electricity Regulatory ... on 23 May, 2012
Chhattisgarh State Power Distribution ... vs Isa Power Pvt. Ltd. & Ors on 17 April, 2012
Kaveri Gas Power Ltd vs The Tamil Nadu Electricity Board & Ors on 24 September