Phodi @ Krishna Upadhyay vs The State Of Madhya Pradesh on 8 February, 2019
1 MCRC-5227-2019
The High Court Of Madhya Pradesh
MCRC ... PHODI @ KRISHNA UPADHYAY Vs THE STATE OF MADHYA PRADESH)
Gwalior, Dated : 08-02-2019
Shri Ajay Kumar Dwivedi, learned counsel for the applicant.
Smt. Gayatri
before
the second respondent - Tahasildar, K.R. Puram, Bengaluru
East Taluk, for phodi durasthi of the said land. The second
respondent - Tahasildar after conducting survey ... said
land, effected phodi durasthi of the same and assigned it
Sy.No.30/1A15 in favour of the appellant - Susairaj vide order
dated
Phodi Alias Krishna Upadhyay vs The State Of Madhya Pradesh on 19 July, 2019
The High Court Of Madhya Pradesh
MCRC-29450-2019
(PHODI @ KRISHNA ... submitted that the
The High Court Of Madhya Pradesh
MCRC-29450-2019
( PHODI @ KRISHNA UPADHYAY Vs THE STATE OF MADHYA PRADESH )
applicant is in custody
Phodi @ Krishna Upadhyay vs The State Of Madhya Pradesh on 5 February, 2019
1 MCRC-5227-2019
The High Court Of Madhya Pradesh
MCRC ... PHODI @ KRISHNA UPADHYAY Vs THE STATE OF MADHYA PRADESH)
1
Gwalior, Dated : 05-02-2019
Shri Shubhendu Chauhan, learned counsel for the applicant.
Smt. Gayatri
father of the defendant Nos.1 and 5.
During the phodi proceedings, it was noticed that actual
extent of land allotted to share of Seenappa ... respondent No.1 was allotted 17
guntas of land during the phodi proceedings as per
akarband the measurement was rectified to 25 guntas
of land
before the respondent No.2
for extraneous reasons seeking for cancellation of phodi
settled on 03.03.2004 alleging that the phodi with
respect ... overlapping with Sy. No.21/1.
Hence, sought for setting aside the phodi and other
revenue documents. Petitioner and respondent No.6
filed their objections
CONSTITUTION OF INDIA PRAYING TO
DIRECT THE 5TH RESPONDENT TO EFFECT THE PHODI
WORK IN RESPECT OF LAND BEARING SY.NO.5/P13,
MEASURING ... which has resulted in filing of this writ
petition seeking to conduct phodi of the extent of land which
is reclaimed by the Government
INDIA PRAYING TO DIRECT THE RESPONDENTS TO
CARRY OUT THE DHURASTHI AND PHODI WORK IN
RESPECT OF THE SCHEDULE LAND DESCRIBED HERE
BELOW ... Mandamus to
direct the respondents to carry out the
Dhurasth and phodi work in respect of
3
the Schedule Land described here
below
therein and therein, he did not get 1 acre. 2nd
respondent got phodi proceedings conducted and got 1
acre of land recognized in phodi proceedings ... falsely got
endorsement that it was served and based on that, phodi
was allegedly conducted, without leaving the road as
required under the partition deed
accepting
plea of the petitioner and directing survey authorities to
carryout phodi and durasthi work in respect of land in
question.
4. In the meanwhile ... came to be acquired is yet to be
adjudicated. On account of phodi and durasthi work
having not been prepared by respondent