Licensee in the State who installs a
solar roof-top plant c) Implementation of roof-top project under
the State Government Scheme by person other ... State who installs a solar roof-top plant. Accordingly, in case of
implementation of solar roof-top project under the aforesaid scheme
by a person
power developer and roof top owner inter
se for the purpose of implementation of roof top installations for group A
projects was executed between ... commissioning of such projects.
Hence, the ESCOMs are directed to ensure completion and
commissioning of the SRTPV projects on existing roofs within
period
expenses relating to relevant project are recorded to that project
account and there after all indirect expenses common to all projects are accounted ... expenses relating to relevant project are recorded to that
project account and thereafter all indirect expenses common to all projects
project. Further, the
Appellant has infused total funds into the project in terms of
equity to ensure timely completion of the project. It is pertinent ... submitted that the purpose of coming out with solar
roof top projects is to enable entities to utilise space on the roof and
to utilize
short BESCOM), the licensee, framed a scheme for
solar roof top projects to be established in the State of Karnataka and
notified the same ... power developer and roof top owner inter
se for the purpose of implementation of roof top installations for group A
projects was executed between
Geyser provisions are given on top floor terrace under
sloping roof projections. Water tank has been provided and everything
was done as per the drawings ... palace.
There is a hydraulic lift, centrally air-conditioned, heat insulation
underneath roof and above POP false ceiling 24 hour genset back-up
with servo
construction taking into consideration of roof to roof area including main building, balconies, staircase, overhead tank slab and roof projection connected. The work was started
inspection, the applicant had further observed defects itemized as below:
(a) Roof projection on Government land at ground and first floor and second floor under
reported that instead of sloping roof flat roof is provided with no roof projection on the eastern side. Thus the quality of the construction
project to be
commissioned by the Respondent at Chacharwadi-
Vasana, Taluka: Sanand, District: Ahmedabad
(Project Site). The Respondent was allowed 2 MW
Solar power project ... Power Project to the nearest sub-station of the
Appellant.
3.5 The Respondent No. 2 has proposed to commission
the project on the Roof