removing unauthorized and illegal construction
of the wall in the setback area on the southern side of the property bearing ... remove/demolish such unauthorized and illegal
construction of wall in the setback area on the southern side of the property
in question.
2. Heard learned
petitioner is not on the road margin, but is on the
setback area of the Manas Sarovar Apartment Complex, and as such, the
notice ... shop is
not on the road margin, but is on the setback area of the apartment
3
complex, it is to be noted that
illegal and unauthorized construction made by
the 6th respondent in the setback area in deviation of the sanctioned plan,
in Plot
permission dt.29.10.2022 have made certain deviations in setback
area and the respondents-authorities by noticing the same have issued a
show cause ... upon the unofficial respondents
to remove the deviations made in the setback area within seven days,
failing which, the unofficial respondents were informed that further
existing road, the proposed road and the required area to be
marked as road affected area; (3) the number of properties that would be
affected ... there being a proposal for widening of the
road, the said setback area would become a fertile ground for being
encroached, which, instead of addressing
from
the petitioner have caused verification and found deviation
in the setback area; and thus, issued a show-cause notice,
dt.29.05.2024
before 01.04.2024 undertaking to remove the construction
5
made in the setback area in deviation of the sanction plan/letter of
approval for commencement
before 01.04.2024 undertaking to remove the construction
5
made in the setback area in deviation of the sanction plan/letter of
approval for commencement
before 01.04.2024 undertaking to remove the construction
5
made in the setback area in deviation of the sanction plan/letter of
approval for commencement
following setbacks while proceeding
with the construction:
Front setback: 3 meters, rear setback: 2 meters, side I
setback: 2 meters and side II setback ... stands redressed on
account of the unofficial respondents leaving the required
setback area and thus, no further orders are necessary.
14. Accordingly, this Writ Petition