sent to the party
indicating the slow progress of work. It is denied that the work was slowed down on the
basis of the instructions ... adjusted
against the losses suffered on account of slow progress of work and the illegal
termination/recession of contract by the plaintiff. It is also
requested the defendant to withdraw the same
as the slow progress of work was caused due to circumstances
beyond the control of plaintiff, and that ... emails dated 19.10.2010, defendant once again
expressed dissatisfaction over the slow work progress and reminded
the plaintiff to send the manpower deployment details
grace
period of 9 months. Only the non completion of work or
slow progress in work does not amount to criminal
liability. There
balance amount. Otherwise also
only the non completion of work or slow progress in work
does not amount to criminal liability. There is no
allegations
asked them to take up works
themselves, however, due to slow progress of works, the contract of TCIL
was terminated by MPRRDA vide letter dated ... asked
them to take up works themselves. Due to slow progress of works,
the contract of TCIL was terminated by MPRRDA vide letter No.
2395
respondent had written number of letters to the claimant regarding
slow progress of work and also evident from the facts that Gujarat
Electricity Board also ... written to the respondent for slow progress of
work. The claimant did not apply for any extension of time nor any
supported documents submitted
damages under Clause
17-B of GCC, claimant/respondent continued executing the work
without any protest and no such issue was ever raised till ... after more than two months from the
awarding of the work, intimating slow progress of work and 7%
approximately work done. 1st extension in date
work within the stipulated time of completion due
to slow progress of work and as such, the extensions were
granted under clause ... respondent cannot be blamed for the slow
progress of the work. The delay in the work was caused due to
change in designs
M/S Ram Niwas Goel vs Municipal Corporation Of Delhi on 22 February, 2025