that all the letters issued by the respondent/Engineer
on slow progress of work and deployment were replied by
him at the contemporaneous time ... Claimant.
AT observes that Engineer, who had commented on slow
progress of work vide various letters relied on by
respondent, had finally considered the totality
show that after 10.10.2003, there was any allegation
of slow progress of the work. Still surprisingly, by the
letter at Ex. R24 dated ... serious complaint was made by Sri Yadiyal that the
progress of work was slow completed Even that the
- 34 -
MFA No.8761 of 2015
Claimant
fine of Rs.1,00,000/- as alleged as slow progress of work.
24. On receipt of the above letter dated 29.10.2010 of the second ... defendant on 15.09.2010, 20.09.2010 and
29.09.2010 because of the slow progress of work done by the plaintiff in the available
ROW. As per the agreement
awarded to a contractor on 03.12.2018 but on account
of slow work progress, the contract was terminated on 08.04.2022. Revised
administrative sanction was accorded vide
awarded to a contractor on 03.12.2018 but on account
of slow work progress, the contract was terminated on 08.04.2022. Revised
administrative sanction was accorded vide
respondents were not correct in
complaining that the progress of the work was slow and that the
respondents are acting in an arbitrary and mala ... completed by 28.11.2024, they cannot blame the
petitioner for the slow progress of work and cannot demand that the
petitioner complete the work by disobeying
materials, is a lame cause put
forth by it, for slow progress of work. It is further contended that after
prolonged correspondence, respondent issued notice ... balance work of package
No.25 on the ground of slow progress of work. Later, even without
issuing any prior notice to the petitioner, respondents
Executive Director of respondent no. 1 / CPWD,
whereby the slow progress of the work was referred and it was inter alia
stated as under ... completion
due to your wrongful delay or suspension of work or slow progress
of work or because of reasons within your control. Therefore, under
expiry of more
than a decade, there has been very slow progress in the work in
question, for ready reference, the order dated ... various bottlenecks as well as on account of the slow
progress of the work being done by the contractor
concerned.
Mr. Navnit Prakash, learned counsel
ground that in the year 2020-2021,
the progress of work is slow and the requisite man-days of work have not
been provided ... progress of works in the Panchayat did not
amount to any major misconduct warranting dismissal from service. Apart
from mentioning that the progress of work