that,
the supplied materials substandard one, accordingly,
legally enforceable liability was not in existence as the
complainant had supplied substandard material.
22. The complainant ... Coil Sheets was substandard? As held supra,
the onus is on the accused to prove the alleged
substandard of material supplied by the complainant
trousers. But, the
complainant company intentionally supplied
substandard quality goods to them. After received of
the substandard materials, they immediately
informed to the complainant company ... about supply
13 C.C.No.32850/2018
of substandard materials through E-mail as well as
What's App along with Photographs
Qaimoh, for doing the electrification,
but BDO Qaimoh has procured the substandard material.
It is also alleged that the Director released an amount ... execute any work in the Panchayat
Ghars but dumped the substandard material through the
team of Engineering Experts and caused loss to the State
Exchequer
concerned for
discharge and further that the petitioners deliberately supplied the substandard
material thereby causing loss to the NHPC and the Managing Director ... obligation to supply the material as per the specifications
prescribed in the contract but they supplied the material that was substandard
present petitioner including other co-accused
persons. Further he submitted that substandard materials were used for
construction which otherwise breached the trust of the State ... seen that the present petitioner being the
contractor had used some substandard materials for construction of the said
stadium with some major deviations
knowledge in
this regard. The MDC concluded that the plaintiff supplied substandard
material without making any independent enquiry with experts in furni-
ture shops ... Given the defendants'
failure to establish that the plaintiff supplied substandard material, the
plaintiff is entitled to the value of the costs
materials to the designated Ashram Schools.
14. The defendants contend that the plaintiff supplied materials of in-
ferior and substandard quality. In response to these ... knowledge in this regard. The MDC concluded that the
plaintiff supplied substandard material without making any independent
enquiry with experts in furniture shops or seeking
knowledge in
this regard. The MDC concluded that the plaintiff supplied substandard
material without making any independent enquiry with experts in furni-
ture shops ... Given the defendants'
failure to establish that the plaintiff supplied substandard material, the
plaintiff is entitled to the value of the costs
ground that the building is being
constructed by using substandard materials and the quality of the
construction is bad and excess amount received than ... respondents and the over
payment made by the appellant and the substandard materials used for
_________
Page
defective designing of
and/or misconduct or negligence in use of substandard materials, etc.
in construction of the subject building complex, complainant have to
suffer ... Page 16 of 41
10.2 That the opponents have used substandard material; they have not
acted as per the approved plan; they have used material