Summary of the affidavit has been shown
as follows:
Phase
1
The
SVNIT has visited 39 units whose trial run of 3/6 months ... Extension
for 3/6 units 31 units = 39 units
Phase
2
The
SVNIT has visited 26 units whose trial run of 3/6 months
JUSTICE MR. S.J. MUKHOPADHAYA)
The
report dated 1.7.2010 submitted by the SVNIT has been enclosed with
the paper book (Phase III, Part - I) covering ... closure and partial closure
of the units, as recommended by the SVNIT and to ensure that trial
run of 3 months at 50% of approved
submitted by the Sardar Vallabhbhai National
Institute of Technology, Surat (for short SVNIT ) in regard to
39 closed industries. After inspection of 39 units ... Tushar Mehta appearing on behalf of Gujarat Pollution
Control Board submits that SVNIT by this time inspected more than 55
units and stated that next
District Valsad, were inspected by Sardar
Vallabhbhai National Institute of Technology, Surat, [SVNIT] under
the supervision of the Gujarat Pollution Control Board. On receiving
adverse ... report from SVNIT, the unit of the petitioner has been
ordered to be closed by the Gujarat Pollution Control Board.
2 Mr.
Sunil L. Mehta
Sardar Vallabhbhai National Institute
of Technology, Surat ( SVNIT for short), visited a number of
industrial units and submitted its report. Having found that a
number ... petition has been preferred. Today it is informed that in the
meanwhile, SVNIT has revisited the unit and allowed trial run for
six months
Sardar Vallabhbhai National Institute of Technology, Surat (for short
SVNIT ).
A
fresh report has been filed on behalf of the 1st
and 2nd
respondent, wherein ... remain closed. Taking
into consideration the aforesaid facts, while we allow the SVNIT to
make further inspection with regard to rest of the industries
invoi/;5invvg_lAi:"2tiie x7'?-iof___thpe Election Rules.
' ~ Svnit;--Geethadevi submits that the petitioners
that they would not take part
years old baby and after the deatlrfzof »yi'fei_i"~SVnit:.
Usha and the granddaughter Anushri were the-L'
appeliant
Industrial Area is going on at the hands of the officers of SVNIT.
The final report in this regard will be submitted after verifying ... measures being taken by the Pollution Control Board and the
monitoring of SVNIT, the effluent being discharged in the sea is not
entirely free from
meantime, as the petitioner has deposited the amount with SVNIT it
may inspect the petitioner industry and submit the report before the
Court. If SVNIT