through government
subsidies or by increasing the tariff. However, the latter may lead
to a tariff shock to consumers in a given year. Hence ... comply with an
APTEL order. To prevent a tariff shock, it allowed recovery of
Rs. 370 crores in that year, and created a regulatory asset
therein the original tariff order was yet to come into
force. And the said application was filed for revision of tariff and
considered in view ... tariff fixation for re-imbursement, as
admissible by the Regulations in the forthcoming
tariff period in a manner that tariff shock
framed tariff regulations, namely, 'Jharkhand State Electricity Regulatory Commission (Tariff) Regulations, 2003'. The JSERC in its power determined the new tariff ... align the tariff structure towards cost of supply during the current year itself, but it was constrained due to the huge tariff shock that
align the tariff structure towards
cost of supply during the current year itself, but it was
constrained due to the huge tariff shock that
cost will constitute the
basis for tariff fixation, and no revision would be entertained
till the next tariff period. This direction presupposes that ... project as well, in the interest of avoidance of
tariff shocks down stream. In case the projects exempted from
CEA clearance, the Commission would consider
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies
Electricity (Supply) Act 1948 requires tariff must be so fixed as to leave no tariff gap and in fact, there should be revenue surplus ... entire revenue requirement during a single year might lead to a tariff shock and so a part of the required revenue is deferred for future
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies