National Tariff Policy and
Commission's own Tariff Regulations provide that cross
subsidy should be reduced gradually so as not give tariff
shock ... Respondent which had
been published and determined tariff giving tariff shock to
subsidized categories of consumers. We are not conveying or
suggesting that the Commission
Tariff Policy according to which the increase in tariff
should be gradual so that there is no tariff shock. Further
there is no rationale ... Respondent which had been published and determined
tariff giving tariff shock to subsidized categories of
consumers. We are not conveying or suggesting that the
Commission
tariff is higher than the tariff
applicable to the state metro rail service .
28.The claim of the appellant for reduction in the tariff ... average tariff realization of that
category of consumers. While the cross-
subsidies have to be reduced progressively and
gradually to avoid tariff shock
tariffs of different categories of
consumers are differentiated only according to the
factors given in Section 62 (3) and there is no tariff
shock ... average tariff realization of that
category of consumers. While the cross-subsidies
have to be reduced progressively and gradually to
avoid tariff shock
crores have been left
un-recovered to avoid tariff shock to consumers. Let
us first examine the observations of the State
Commission in the impugned ... year an average
increase in tariff of 22% will be required which will
result in tariff shock to the consumers in the state.
14.194 Accordingly
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies
Mawana Sugars Ltd vs Punjab State Electricity Regulatory ... on 12 July, 2012
BEFORE THE APPELLATE
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies
empowers the appropriate Commission
to pass provisional tariff order under Section 94(2) till the final tariff order
27
is passed under Section ... interest of consumers i.e., to save the consumer from
tariff shock on final determination and also to keep the project of the
generating companies