Tamil Nadu Electricity Regulatory Commission (for
short ‘TNERC’) and the APTEL have concurrently found in
favour of the respondent. It has been held that ... calculated as per the formula pursuant to Section
7.3.”
FINDINGS OF THE TNERC:-
5. The TNERC recorded the following findings: -
Page
arbitrary, illegal and contrary to the
provisions of the Hon'ble TNERC'S Open Access Regulations, 2014 and the
consequent orders passed ... TNERC and consequently direct
the respondents to adjust/refund the said charges collected and forbear the
_________
Page
Tamil Nadu Electricity Regulatory Commission,
TNERC, 4th Floor, SIDCO Corporate Office building,
Thiru Vi Ka Industrial Estate, Guindy,
Chennai, 600 032. ... Respondents
Prayer: Writ Petition ... tariff system) under the respective
tariff orders issued by the 5th Respondent TNERC for the period from 01.08.2017
to 30.06.2024 and the consequential demand notice
energy. And, if a dispute arises it should be resolved only
through TNERC.
3. The issue involved is short as to whether the petitioner ... judis
W.P.No.19552 of 2020
decided only by TNERC, which implied the petition possibly is not
entertainable.
4. Heard Mr.S.P.Parthasarathy
Tamil Nadu Electricity Regulatory Commission,
TNERC, 4th floor, SIDCO Corporate Office building,
Thiru Vi Ka Industrial Estate, Guindy,
Chennai 600 032. ... Respondents
Prayer: Writ petition ... tariff system) under the respective tariff
orders issued by the fifth respondent TNERC for the period from
01.08.2017 to 30.06.2024 and the consequential demand notice
Tamil Nadu Electricity Regulatory Commission,
TNERC, 4th floor, SIDCO Corporate Office building,
Thiru Vi Ka Industrial Estate, Guindy,
Chennai 600 032. ... Respondents
Prayer: Writ petition ... tariff system)
under the respective tariff orders issued by the fifth respondent TNERC
for the period from 01.08.2017 to 30.06.2024 and the consequential
demand notice
TNPDCL, Anna Salai
Chennai – 600 002.
5.Tamil Nadu Electricity Regulatory Commission,
TNERC,
4th Floor, SIDCO Corporate Office building,
Thiru Vi Ka Industrial Estate,
Guindy ... tariff
system)under the respective tariff orders issued by the 5th respondent
TNERC for the period from 1.8.2017 to 30.6.2024 and the consequential
demand notice
TNPDCL, Anna Salai
Chennai – 600 002.
5.Tamil Nadu Electricity Regulatory Commission,
TNERC,
4th Floor, SIDCO Corporate Office building,
Thiru Vi Ka Industrial Estate,
Guindy ... tariff
system) under the respective tariff orders issued by the 5th Respondent
TNERC for the period from 01.08.2017 to 30.06.2024 and the consequential
demand notice
Tamil Nadu Electricity Regulatory Commission,
TNERC, 4th floor, SIDCO Corporate Office building,
Thiru Vi Ka Industrial Estate, Guindy,
Chennai 600 032. ... Respondents
Prayer: Writ petition ... tariff system) under the respective tariff
orders issued by the fifth respondent TNERC for the period from
01.08.2017 to 30.06.2024 and the consequential demand notice
TNPDCL, Anna Salai
Chennai 600 002.
5. Tamil Nadu Electricity Regulatory Commission,
TNERC,
4th Floor, SIDCO Corporate Office Building,
Thiru Vi Ka Industrial Estate,
Guindy ... prevailing valid and enforceable tariff order issued by the 5th respondent
TNERC for start-up power, for the period from July 2024, as being arbitrary