propriety of the Tamil Nadu Electricity
Regulatory Commission's ("TNERC") Order dated 31.03.2016 in
Petition No. 5 of 2016 ("Impugned Order ... Petition") was filed by Biomass Power before
the Respondent No. 1 / TNERC, for seeking tariff revisions for both
existing and new plants.
2. Brief
before Tamil Nadu
Electricity Regulatory Commission (hereinafter variously referred to as
"TNERC" or "State Commission") on Petitions registered ... light of separate findings
recorded by the two members of the TNERC".
8. The three other appeals were preferred by Indian Wind Power
Association
GERC),
Maharashtra Electricity Regulatory Commission (MERC) and Tamil
Nadu Electricity Regulatory Commission (TNERC) do not approve
individual PPAs for renewable energy projects. It is argued ... made to the process
followed by other regulators (CERC, GERC, MERC and TNERC) is of no
consequence in view of the framework
Tamil Nadu
Electricity Regulatory Commission (hereinafter referred to as "TNERC"
Appeal No. 188 of 2019 & IA No.980 of 2019 Page
Page 2 of 8
"Commission" or "TNERC"), had issued a Tariff Order dated June, 2013
based on the Tariff Petition filed
account of the order
received from Tamil Nadu Electricity Regulatory Commission [TNERC] vide
order dated 17.06.2011. The said amount of Rs.566.64 crores related
Tamil Nadu Electricity Regulatory
Commission (hereinafter referred to variously as "TNERC" or "State
Commission" or "Commission"), the Appellant ... coming
through only in July, 2019. Thus, when the two members of TNERC who
had continued to hold office proceeded to hear the matters arising