introduced by the Tamil Nadu Electricity Regulatory Commission
(hereinafter referred as 'TNERC') by issuing a Tariff Order. Under the
Merit Order Ranking regime ... TNERC places plants in the State of Tamil
Nadu in the order of their variable cost with the cheapest plant placed at
the highest level
introduced by the Tamil Nadu Electricity Regulatory Commission
(hereinafter referred as 'TNERC') by issuing a Tariff Order. Under the
Merit Order Ranking regime ... TNERC places plants in the State of Tamil
Nadu in the order of their variable cost with the cheapest plant placed at
the highest level
introduced by the Tamil Nadu Electricity Regulatory Commission
(hereinafter referred as 'TNERC') by issuing a Tariff Order. Under the
Merit Order Ranking regime ... TNERC places plants in the State of Tamil
Nadu in the order of their variable cost with the cheapest plant placed at
the highest level
adopted
CUP method by considering Power Purchase Agreement entered into by
the TNERC with various power generators, where, the TNERC has fixed
tariff ranging from ... into similar kind of business, then, the
TPO adopting rate charged by TNERC for power suppliers, is incorrect.
The assessee had also relied upon certain
should not procure
energy from other sources.
2. Clause 12(2) of TNERC's Grid Connectivity and Intra State Open Access
Regulation, 2014, provides ... sought."
3. The objection now revolves around clause 12(2) of TNERCs Grid
connectivity and Intra State Open Access Regulation, 2014, and Clause
should not procure energy from
other sources.
2. Clause 12(2) of TNERC's Grid Connectivity and Intra State Open Access
Regulation, 2014, provides ... sought."
3. The objection now revolves around clause 12(2) of TNERCs Grid
connectivity and Intra State Open Access Regulation, 2014, and Clause
issue working instructions in order to implement the Hon'ble TNERC Order
in DRP No.19 of 2013 dated 19.01.2015 which has also ... implement the order
of third and fourth respondents Hon'ble TNERC's Order in RA No.6 of 2013
dated
issue working
instructions in order to implement the Hon'ble TNERC order in DRP No.19
of 2013 dated 19.1.2015 which has also ... also to implement the order of 3 rd
respondent Hon'ble TNERCs order in R.A. No.06 of 2013 dated
issue working instructions in order to implement the Hon'ble TNERC Order
in DRP No.19 of 2013 dated 19.01.2015 which has also ... implement the order
of third and fourth respondents Hon'ble TNERC's Order in RA No.6 of 2013
dated
said
demand made by the appellant was not in consonance with the TNERC
Distribution Code as well as it is against the practice hitherto being ... learned Single Judge in the impugned order is against Clause
34 of TNERC Distribution Code. Therefore, on that ground, the order
impugned can be successfully