installment of Rs.33 Lakhs could not be paid because of
certain unavoidable circumstances and that Respondent Nos.
Jyoti Mane 4 of 6
::: Uploaded
Vestas Wind Technology India Private ... vs M/S. Inox Renewables Limited And 3 Ors on
petitioner for re-
scheduling the dates till 15th August, 2013 due to unavoidable circumstances set
out in the said application. He submits that the petitioner ... such
cost for the re-schedulement in view of the genuine and unavoidable circumstances
placed on record by the petitioner.
30. It is submitted that
there
being a large number of unit holders and various other unavoidable
reasons. Such Deeds of Apartments could be executed only by the
respondent
party to file pleadings or documents by few days though due to unavoidable
circumstances.
43. In my view, the word 'shall' used
M/S. Gujarat Fluorochemicals Limited vs Vestas Wind Technology India Private ... on 1 April, 2019
Amritlal Versi Malde And Anr vs National (India) Contractors And ... on 20 April, 2021
Author
Provided that, if owing to urgent necessity or
unavoidable accident all such persons do not so appear, the
Registrar, in cases where the delay
evidence. It is the case of the applicant that due to
unavoidable circumstances, the applicant could not file affidavit of evidence
::: Uploaded
electric meter. The learned counsel suggests that in view of these unavoidable
circumstances, the court can consider to issue notice upon the said Adani
Electricity