Larsen & Toubro Limited vs Sanghi Industries Limited on 25 February, 2022
Author: Adarsh Kumar
dealt
contingent contract as defined in the Indian Contract Act, 1872 .
We have gone through the said judgement and find that a
contract which ... future
uncertain event cannot be enforced by law unless and until that
event has happened. If the event becomes impossible/uncertain
such contract becomes void
being a prudent
business man the assessee entered into foreign currency
forward contract in respect of receivable / payable from
its exports / import orders in order ... 2015.
V. Vinodkumar Diamonds P. Ltd..
- 12 -
uncertain forward contracts were restated at the yearend
applying the closing rate of the foreign currency and gain
acts, as the number of service calls during the contract period is
uncertain and cannot be predetermined. At the same time, the services are
rendered ... completion method except for
certain service contracts, and that the contract revenue shall include retention
money, and contract cost shall not be reduced by incidental
Civil Court for specific performance of contract which
is still pending and hence his complaint is not maintainable.
7. The
learned Advocate of the appellants ... held that if the terms of the contract are vague and uncertain, the contract
itself is void and un enforceable
Civil Court for specific performance of contract which
is still pending and hence his complaint is not maintainable.
7. The
learned Advocate of the appellants ... held that if the terms of the contract are vague and uncertain, the contract
itself is void and un enforceable
contract subject to
happening of the stated event(s).
8
"31. ‗Contingent Contract' defined - A
‗contingent contract' is a contract ... contracts
become void.
33. Enforcement of contracts contingent on an
event not happening - Contingent contracts to
do or not to do anything if an uncertain
M/S. Modi Industries Ltd,, Uttar ... vs Dcit, New Delhi on 24 August, 2017
INCOME
crores.During the assessment proceedings,the AO found that assessee got a contract from
IOC,in Panipat Naptha Cracker Unit, that it had claimed anticipated ... cases,that in the case under consideration contract was yet to be executed, that
the losses were uncertain.He disallowed the claim made
last date of the relevant previous year,
the forward contract was subsisting and was not settled. The Assessee as on the last date ... existing liabilities and assets. Future sales were uncertain and hedging such
future sales through forward contracts was purely a speculative transaction. Loss not
arising