valid PPA. This judgment is also not relevant in
the present case as the PPA was entered into by the
parties, but was only required ... held as under:
"When an agreement is entered into subject to
ratification by others, a concluded contract is not
arrived at. Whenever ratification
basis of the final decision taken by the Board is
perfectly valid.
6. Having regard to the rival contentions of the parties, the core
issue ... parties is binding
on the parties in the absence of the ratification by
the Whole Time Directors of the Electricity Board,
the Respondent?
7. Before
sale and referred
the matter to the third respondent, who had a valid
PPA with the appellant, then the appellant sent an
email ... agreement is entered into subject to ratification by
others, a concluded contract is not arrived at.
Whenever ratification by some other persons, who are
parties
Talwandi Sabo Power Limited vs Punjab State Electricity Regulatory ... on 4 July, 2017
Apl-32.15
Azure Photovoltaic Private Limited vs Gulbarga Electricity Supply Company ... on 12 August, 2021
Judgment in
Gvk Power (Goindwal Sahib) Limited vs Punjab State Power Corporation Limited ... on 26 February, 2020
Adani Green Energy (Up) Limited vs Karnataka Electricity Regulatory ... on 14 May, 2024
IN THE
intact till the DERC revises the same. As, there was no
ratification of Cross Subsidy Surcharge (CSS) by the Hon'ble
DERC ... Surcharge amount.
So, the allegations of the Appellant are not at all valid and are
irrelevant in the present context.
Moreover, the Delhi Electricity Regulatory
Vbc Ferro Alloys Limited vs Karnataka Electricity Regulatory ... on 7 October, 2013
Appeal No.80
Reliance Infrastructure Limited vs The Maharashtra Electricity ... on 23 March, 2012
Judgment in Appeal No