Supreme Court of India

Jagdish Chand Radhey Shyam vs The State Of Punjab And Others on 6 September, 1972

Equivalent citations: 1972 AIR 2587, 1973 SCR (2) 97, AIR 1972 SUPREME COURT 2587, 1973 3 SCC 428, 1974 2 SCJ 255, 1973 (1) SCJ 614, 1973 2 SCR 97, 1972 CURLJ 973

Author: A.N. Ray

Bench: A.N. Ray, I.D. Dua, Kuttyil Kurien Mathew

           PETITIONER:
JAGDISH CHAND RADHEY SHYAM

	Vs.

RESPONDENT:
THE STATE OF PUNJAB AND OTHERS

DATE OF JUDGMENT06/09/1972

BENCH:
RAY, A.N.
BENCH:
RAY, A.N.
DUA, I.D.
MATHEW, KUTTYIL KURIEN

CITATION:
 1972 AIR 2587		  1973 SCR  (2)	 97


ACT:
Constitution  of India-Articles 14 and 19(1) (f) Capital  of
Punjab	(Development  and Regulation)  Act  1952-Section  9,
forfeiture  of the whole or any part of consideration  money
for  breach of non-payment of the balance-Whether  violative
of Art. 14 of the Constitution of India-- Resumption of site
for unpaid consideration money--Whether violates Article  14
of the Constitution.
Section	 9,  resumption	 of site  for  unpaid  consideration
amount	 whether   violates   Article	19(1)(f)   of	 the
Constitution.



HEADNOTE:
The  appellant purchased a site at a public auction for	 Rs.
94,000,-.  25% of the price, i.e. Rs. 23,500/- was  paid  at
the  site  and	the balance was to be paid  in	three  equal
installments.	The  appellant	paid a further	sum  of	 Rs.
21,992/-  towards the first instalment.	 Two instalments  of
Rs.  25,615/- each and sum of Rs. 3,623/- being the  balance
sum of the first instalment were not paid by the  appellant.
The Estate Officer, in exercise of powers under section 9 of
the  Capital  of Punjab (Development  and  Regulation)	Act,
1952,  resumed	the  site and forfeited	 the  amount  of  Rs
42,728.01  paid	 by  the appellant.   After  exhausting	 his
remedies  under	 the  Act,  the	 appellant  challenged	 the
validity of the orders and vires of Section 9 of the Act  on
the ground that provisions of Section 9 regarding forfeiture
of  the instalments paid and the resumption of	the  auction
site were violative of Article 14.  The power of  resumption
of  site under section 9 was also challenged as	 unconstitu-
tional	 on   the  ground  that	 it   imposed	unreasonable
restriction  on	 the  right to	property  violating  Article
19(1)(f)  of the Constitution.	The Punjab High	 Court	held
that  the  Government had right to resume the site  as	they
were the owners and till all the instalments were not  paid,
the  title did not pass to the auction purchaser.  The	High
Court also held that is the Government have power to recover
the  due  amount as arrears of land revenue,  resumption  of
site was not illegal.
HELD : The Prohibition in Section 3 of the Act against sale.
mortgage  or transfer, by the auction purchaser except	with
the previous permission of the Estate Officer of any  right,
title  or interest in the site or building,  recognises	 the
ownership  rights of the purchaser.. The Government is	only
entitled, to a charge on the property for the unpaid portion
of  the consideration money.  A charge on property is  under
the Transfer of Property Act enforced by instituting a	suit
and  bringing  property	 to  sale.  Section  8	of  the	 Act
provides  another  power to the Government  to	recover	 the unpai
d money as arrears of land revenue. [100 E-101-A]
Section 9 of the Act empowers the Government to forfeit	 the
whole  or  any part of the money in case of  non-payment  of
consideration  money or instalments or other dues or  breach
of  covenant,-,.  Under the ordinary law of the land,  there
is  relief  against  forfeiture	 for  breach  of   covenant.
Section 9 does not offer any relief against forfeiture.	 The
Government  can	 proceed  eitheir  under  the  Transfer	  of
Property Act
8-L348Sup.C.I./73
98
or under the present Act without any guidelines provided  in
the  statute.  This feature makes section  9  discriminatory
and violative of Article 14 of the Constitution of India.
Section	 9  also confers power to resume  the  site.   Where
there is a charge, the same can be enforced by instituting a
suit in a court of law under Transfer of Property Act.	 The
owner  will  have  an opportunity of paying  the  money	 and
clearing the property of the charge.  No such opportunity of
clearing the charge is possible under section 9 of the	Act.
There  is no guideline in the Act as to when the  Government
will  resort to resumption of site or forfeiture of  monies.
The Government choose without any guideline and discriminate
in proceeding against one person in one manner and a  second
one in other manner.
In the teeth of statutory security and enforceability of the
Government  charge  in preference to others, it	 is  totally
unreasonable  restriction  on the enjoyment of	property  by
resuming  site	for  defaults  in  payments  of	 money	 and
forfeiting  the	 monies paid by the transferee.	  Section  9
violates Article 19(1)(f). [101 C-102A]



JUDGMENT:

CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1099 of 1967.

Appeal by certificate from the judgment and order dated 21st February 1966 of the Punjab High Court, Chandigarh in Letters Patent Appeal No. 218 of 1965.

Mahendrajit Singh and K. B. Mehta for the appellant. Harbans Singh and R. N. Sachthey for respondents. The Judgment of the Court was delivered by RAY, J. This appeal is by certificate from the judgment dated 21 February, 1966 of the High Court of Punjab and Haryana it Chandigarh.

The appellant at a public auction held by the Estate Officer. Capital Project, Chandigarh on 21 December, 1958 purchased site No. 43 in the Grain Market, Chandigarh. The purchase price was Rs. 94,000. 25% of the sale price was payable at the fall of the hammer. The balance sum with interest was payable in three equalinstallments of Rs. 25,615 each. The appellant paid 23, 500 being 25% of the sale price at the fall of the hammer. The appellant paid a further sum of Rs. 21,992 towards the first instalment. A sum of Rs. 3,623 was outstanding on the first instalment. The appellant made improvements on the site. The appellant raised construction thereon at his own expense. He invested about Rs. 1,50,000 in the shape of building and machinery. The appellant could not pay Rs 3,623 being the balance of the first. instalment and the second and the third instalments. amounting to Rs. 25,615 each.

99

The appellant asked for instalments because the appellant was in financial difficulty. Eventually, the Estate Officer on 2 January, 1962 resumed the site and forfeited the amount of Rs. 42,728.01 paid by the appellant. The order of resumption and forfeiture was made by the Estate Officer (Capital Project), Cliandigarh in exercise of powers under section 9 of the Capital of Punjab (Development and Regulation) Act, 1952 referred to as the 1952 Act. The appellant filed an appeal under section 10 of the 1952 Act. The appellant's appeal was accepted by the Appellate Authority, the Chief Administrator, Chandigarh. The appellant was given time for the payment of instalments with interest at the rate of 4 1/2% per annum and a penalty of 10 per cent of the amount in arrears was ordered to be paid within 30 days from the date of the Appellate order. The conveyance deed in respect of the site was also to be executed immediately.

The appellant thereafter made a representation to the Chief Minister and asked for further instalments and prayed that steps be not taken to resume the site. The appellant's representation was rejected.

The appellant then filed a revision application before the Financial Commissioner. On 14 September, 1964 the Financial Commissioner rejected the revision application. The ground was that the appellant had filed a first revision application. The second application was therefore not competent. It may be stated here that section 10 aforesaid provides an appeal to the Chief Administrator against the order of the Estate Officer. Section 10 also states that a revision application can be presented before the State Government against the order of the Chief Administrator. The appellant filed a writ petition in the High Court. The appellant challenged the validity of the orders of the respondents. The grounds for challenge were these. First, section 9 of the 1952 Act which provides for the resumption of property by the Estate Officer is ultra vires and unconstitutional. Secondly, section 9 provides for resumption of property and forfeiture of money paid which are unconstitutional and unreasonable restrictions on the right to hold property. Thirdly, the power conferred on the Estate Officer to take action under section 9 for resumption is unregulated and arbitrary.

In the High Court is was contended that the appellant became owner of the site, and, therefore, no resumption of the site could be taken by proceeding under the Punjab Public Premises and Land (Eviction and Rent Recovery Act, 1959. Secondly, it was contended that section 9 of the 1952 Act violated Article 14 100 inasmuch as sections 8 and 9 of the 1952 Act provide for the same matter and there is no indication as to when action will be taken under either of the sections. It was also said that the sections offended Article 14 of the Constitution by reason of unregulated conferment of power. The High Court held that title would pass only when full price was paid and till then the Government remained the owner and could resume possession. The High Court held that sections 8 and 9 of the 1952 Act were supplementary to each other and if recovery of the amount due as arrears of land revenue was provided tat there could be, resumption of the site.

Counsel for the appellant repeated the contentions which had been made before the High Court.

Broadly stated section 3 of the 1952 Act indicate these fea- tures. The Government has power to sell by auction, allotment or otherwise any land or building. The consideration money is to be paid in such manner as the Government may prescribe. The unpaid portion of the consideration money will be a first charge on the site or the building. The transferee except with the previous permission in writing of the Estate Officer shall not be entitled to sell, mortgage or otherwise transfer any right, title or interest in the site or building until the amount which is a first charge has been paid in full. Section 3 totally repels the conclusion arrived at by the High Court that the Government remains the owner until the entire Consideration money is paid. A charge is created for the unpaid portion of the consideration money. The prohibition against sale, mortgage or transfer by the transferee except with the previous permission of the Estate Officer of any right, title or interest in the site or building establishes the ownership and rights of the transferee. If the Government were the owner it could not be said that the transferee could sell, mortgage or transfer any right, title or interest. The statute speaks of payment of consideration money by and sale to the transferee. The Government cannot after sale remain the owner. The Statute forbids such construction. If the Government is the owner the Government cannot at the same time be entitled to a charge on the property for the balance of the consideration money. A charge on a property is under the Transfer of Property Act enforced by instituting a suit and bringing the property to sale. If the property yields a higher price then what the charge represents, the owner is entitled to the excess sum. Section 8 of the 1952 Act deals with imposition of penalty and mode of recovery of arrears. If there is any default in payment of consideration money or instalment or any other money 101 due on account of transfer or if there is default in the payment of fee or tax levied the Estate Officer may direct a sum not exceeding that amount due to be recovered by way of penalty. The amount due together with the penalty may recovered as an arrears of land revenue.

Section 9 speaks of resumption of the site or building by the Estate Officer and forfeiture of the whole or part of the money paid on account of consideration in the case of non-payment of consideration money or instalment or breach of any condition of transfer or breach of any rule. Under the ordinary law of the land it is open to the Govern- ment to enforce the charge and to recover the due on consideration money, instahnents or any other due from the transferee. It is also open to the Government under section 8 of the Act to proceed against the transferee to realise the amount due on consideration money or on instalment or any other due as an arrear of land revenue. Section 8 provides penalty for default in payment of money and the recovery of the same as an arrear of land revenue. These remedies are deterrent and drastic.

Section 9 of the 1952 Act empowers the Government to forfeit the whole or any part of the, money in case of nonpayment of consideration money or instalments or other dues for breach of covenants, Under the ordinary law of the land there is relief against forfeiture for breach of covenant or provisions. Section 9 does not offer any relief against forfeiture. This feature that the Government can proceed either under the ordinary law of the land or under the 1952 Act shows that there is discrimination. There is nothing in the statute to guide the exercise of power by the Government as to when and how one of the methods will be chosen. Section 9 confers power to resume site. There is a charge on the land for the unpaid consideration money. This charge can be enforced by instituting a suit in a court of law. The owner will have the opportunity of paying the money and clearing the property of the charge. on the other hand when the Government proceeds under section 9 of the Act to resume the land or building the Government proceeds under the Punjab public Premises and Land (Eviction and Rent Recovery) Act, 1959. There is no guidance in the Act as to when the, Government will resort to either of the remedies. Again in all these cases of recovery of money or resumption of land or building and forfeiture of monies paid the Government may choose and discriminate, in proceeding against one person in one manner and another person in another manner.

102

The Act creates a charge on the property. The Act forbids creation of a third part right by the transferee until the amount represented by the charge is paid in full. In the teeth of statutory security and enforceability it is totally unreasonable restriction on the enjoyment of property by resuming the site for defaults in payments of money and forfeiting the monies paid by the transferee. For these reasons, we are of opinion that the Government is not entitled to forfeit the monies paid and resume the site under the provision contained in section 9 of the 1952 Act. These provisions violate Articles 14 and 19(1)(f). These provisions are unconstitutional.

The judgment of the High Court is set aside. The appeal is allowed. In view of the fact that there is no order as to costs in the High Court the parties will pay and bear their own costs.

S.B.W.						      Appeal
allowed..