Union of India - Subsection

Section 21(3) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(3)In case of additional costs on account of IDC and IEDC due to delay in achieving the COD, the generating company or the transmission licensee as the case may be, shall be required to furnish detailed justifications with supporting documents for such delay including prudent phasing of funds in case of IDC and details of IEDC during the period of delay and liquidated damages recovered or recoverable corresponding to the delay.