Section 21 in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

21. Interest During Construction (IDC) and Incidental Expenditure during Construction (IEDC).

(1)Interest during construction (IDC) shall be computed corresponding to the loan from the date of infusion of debt fund, and after taking into account the prudent phasing of funds upto SCOD.
(2)Incidental expenditure during construction (IEDC) shall be computed from the zero date, taking into account pre-operative expenses upto SCOD:Provided that any revenue earned during construction period up to SCOD on account of interest on deposits or advances, or any other receipts shall be taken into account for reduction in incidental expenditure during construction.
(3)In case of additional costs on account of IDC and IEDC due to delay in achieving the COD, the generating company or the transmission licensee as the case may be, shall be required to furnish detailed justifications with supporting documents for such delay including prudent phasing of funds in case of IDC and details of IEDC during the period of delay and liquidated damages recovered or recoverable corresponding to the delay.
(4)If the delay in achieving the COD is not attributable to the generating company or the transmission licensee, IDC and IEDC beyond SCOD may be allowed after prudence check and the liquidated damages, if any, recovered from the contractor or supplier or agency shall be adjusted in the capital cost of the generating station or the transmission system, as the case may be.
(5)If the delay in achieving the COD is attributable either in entirety on in part to the generating company or the transmission licensee or its contractor or supplier or agency, in such cases, IDC and IEDC beyond SCOD may be disallowed after prudence check either in entirety or on pro-rata basis corresponding to the period of delay not condoned and the liquidated damages, if any, recovered from the contractor or supplier or agency shall be retained by the generating company or the transmission licensee, as the case may be.