Section 5(5)(c) in The West Bengal Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2011
(c)Where the actual cost incurred on a capital expenditure project exceeds or is likely to exceed the estimate of original project cost, then the licensee or generating company shall apply to the Commission for approval for variation in the estimate of original project cost with supporting documents and proper justification of variation of cost.