1. Allotments of Plots.
- The allotment of plots/sheds will be on an ongoing basis in the following cases as provided in the Industrial Policy 2005 :-1. Projects having investment of Rs. 30 crore and above.
2. Projects being set up by NRIs/PIOs.
3. Units with 33% or more FDI in total investment.
4. Allotment of land for IT Industry (Manufacturing and Software Development).
The applications for the categories 1 to 3 will be processed by the Investment Promotion Centre and for Category 4, the applications will be processed by Department of Industries and Commerce, Haryana.Besides the above, the allotment of plots/sheds in Industrial Estates falling in Category C, will also be on on-going basis.For other categories, allotments will be made after inviting applications through advertisements in leading newspapers.1. Allotment of plots to projects having investment of Rs. 30/- crore and above will be made by the following committee :-
| (a) Principal Secretary Industries | Chairman |
| (b) MD, HSIDC | Member |
| (c) MD, HFC | Member |
| (d) Director of Industries | Member |
2. For other projects including those under FDI, NRI, PIO's categories, IT Industry (Manufacturing and Software Development) and general category, allotments will be made by the following committee :-
| (a) Director of Industries | Member |
| (b) MD, HSIDC | Member |
| (c) MD, HFC | Member |
3. There will be 10% reservation of plots/sheds in each Estate for allotment to NRIs/PIOs and for units with 33% or more FDI in total investment.
4. Preference will be given to the following categories of entrepreneurs :-
* Ex-servicemen* Women* Unemployed Engineering Graduates/Polytechnic/ITI trained candidates* Expansion/Shifting of existing units.* Oustees on account of acquisition of land for that particular Estate within the terms and conditions of EMP.5. Banking and Insurance Facilities shall also be allowed in industrial areas for providing support to the user industry.
Payment terms. - (i) 10% alongwith application (earnest money)1. Taking over possession of the plot.
2. Submission of building plans.
3. Placement of orders of machinery and other capital goods.
4. Financial tie-ups.
5. Technical and marketing tie-up.
The period for implementation of the project can be extended by Director of Industries for a period of one year subject to the allottee having completed construction equivalent to 20% of Permissible Covered Area (PCA) in case of plot size is upto one acre and 10% of PC in case plot size is more than one acre. Further, the allottee will satisfy the department that he could not go into production within three years from the date of offer of possession for reasons beyond his control and he took effective steps for implementation of the project.Second extension of one year for completion of project i.e. after four years from the offer of possession will be granted only in exceptional circumstances with the approval of Government.In case of sheds, the allottee shall be required to implement the project within two years from the date of offer of possession. The period for starting production shall be extended by one year in those cases where the allottee has installed/placed orders for substantial part of plant and machinery and depending on merit of each case.The allottee shall be required to pay extension fee prescribed for that area and the payment shall be made w.e.f. the date the extension is applicable and for any delayed payment interest @ 11% shall be charged.Extension fee at following rates shall be charged :-| Sr. No. | Category | Plots | Sheds | |
| (Rs. per sq. mtr.) | (Rs. per sq. ft. covered area) | |||
| 1st year | 2nd year | |||
| 1 | 2 | 3 | 4 | |
| 1. | Category `A' | 75 | 150 | 30 |
| 2. | Category `B' | 40 | 80 | 15 |
| 3. | Category `C' | 15 | 30 | 6 |
| 1. Upto 1 acre | 25% of PCA |
| 2. Above 1 acre upto 5 acres | 20% of PCA |
| 3. Above 5 acres and upto 10 acres | 15% of PCA |
| 4. Above 10 acres | 10% of PCA |
| Sr. No. | Category | Plots | Sheds |
| (Rs. per sq. mtr.) | (Rs. per sq.ft. of covered area) | ||
| 1 | 2 | 3 | 4 |
| 1. | Category `A' | 300 | 60 |
| 2. | Category `B' | 100 | 40 |
| 3. | Category `C' | 30 | 15 |
| Leasing period upto 5 years | 10% of the transfer fee |
| Leasing period more than 5 years | 25% transfer fee |
| Leasing period upto 5 years | 50% of the transfer fee |
| Leasing period more than 5 years | 100% transfer fee |
| Plot size (square meters) | Maximum number of leases |
| Upto 500 | 1 |
| More than 500 and upto 1500 | 2 |
| Above 1500 | 3 |