State of Bihar - Subsection

Section 25(2) in Bihar Electricity Regulatory Commission (Standards of Performance of Distribution Licensee) Regulations, 2006

(2)The summary of overall performance standards is as follows :
  Service area Overall standard of performance
a Normal fuse-off calls At least 95% calls received should be rectified withinprescribed time limits
b Line Breakdowns At least 95% of cases should be resolved within prescribedtime limits.
c Distribution Transformer (DTR) failure At least 95% of DTRs to be replaced within prescribed timelimits.
d Period of scheduled outage  
  Maximum duration in a single stretch At least 95% of cases resolved within time limit
  Restoration of supply by 6.00 PM
e Street Light Faults  
  Rectification of line faults At least 90% of cases resolved within time limits
  Replacement of fused/defective unit
f Billing mistakes Not exceeding 1%
g Faulty meters Not exceeding 3%
h Voltage unbalance Maximum of 3% at the point of commencement of supply.
i Release of new connection/additional load/Temporary connection 100% cases within specified time limits
k Transfer of Ownership and Conversion of Service At least 98% of cases within specified time limits.