Union of India - Section

Section 5 in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

5. Trial Run and Trial Operation.

(1)Trial Run in relation to generating station or unit thereof shall mean the successful running of the generating station or unit thereof at maximum continuous rating or installed capacity for continuous period of 72 hours in case of unit of a thermal generating station or unit thereof and 12 hours in case of a unit of a hydro generating station or unit thereof:Provided that where the beneficiaries have been tied up for purchasing power from the generating station, the trial run shall commence after seven days notice by the generating company to the beneficiaries.
(2)Trial operation in relation to a transmission system or an element thereof shall mean successful charging of the transmission system or an element thereof for 24 hours at continuous flow of power, and communication signal from sending end to receiving end and with requisite metering system, telemetry and protection system in service enclosing certificate to that effect from concerned Regional Load Dispatch Centre.Chapter - 3 Procedure for Tariff Determination