Section 5(1) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(1)Trial Run in relation to generating station or unit thereof shall mean the successful running of the generating station or unit thereof at maximum continuous rating or installed capacity for continuous period of 72 hours in case of unit of a thermal generating station or unit thereof and 12 hours in case of a unit of a hydro generating station or unit thereof:Provided that where the beneficiaries have been tied up for purchasing power from the generating station, the trial run shall commence after seven days notice by the generating company to the beneficiaries.