State of Tamilnadu - Subsection

Section 13(ii) in The Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2004

(ii)[ The application shall contain the details, such as capacity needed, point or points of injection, point or points of drawal, duration for availing of open access, peak load, average load and such other additional information that may be laid down by the Regional Load Despatch Centre; [Substituted by Notification No. L-7/25(5)/2003-CERC dated 21.02.2005, w.e.f. 1.4.2005.]