Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Section 9(1)] [Section 9] [Entire Act]

State of Rajasthan - Subsection

Section 9(1)(a) in Rajasthan Electricity Regulatory Commission (tariff for Captive Power Plants) Regulations, 2007

(a)The connectivity of CPP to Grid or State transmission system shall be governed by the connection conditions stipulated under State Grid Code and Connectivity Regulations of Central Electricity Authority, as & when notified in accordance with sub-section (b) of Section 73 of the Electricity Act 2003.