Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Section 16(4)] [Section 16] [Entire Act]

Union of India - Subsection

Section 16(4)(a) in Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010

(a)[ MW and MVAR Data for injection or drawal at various nodes or a group of nodes shall be submitted for maximum injection/maximum withdrawal for each application period. Such data shall include the power tied in long term contracts and approved medium term open access agreements.] [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).]