Union of India - Act
Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010
UNION OF INDIA
India
India
Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010
Rule CENTRAL-ELECTRICITY-REGULATORY-COMMISSION-SHARING-OF-INTER-STATE-TRANSMISSION-CHARGES-AND-LOSSES-REGULATIONS-2010 of 2010
- Published on 15 June 2010
- Commenced on 15 June 2010
- [This is the version of this document from 15 June 2010.]
- [Note: The original publication document is not available and this content could not be verified.]
Chapter 1
Preliminary
1. Short title, extent and commencement.
2. Definitions.
Chapter 2
Scope of The Regulations
3.
Yearly Transmission Charges, revenue requirement on account of foreign exchange rate variation, changes in interest rates etc. as approved by the Commission and Losses shall be shared amongst the following categories of Designated ISTS Customers who use the ISTS:-Chapter 3
Principles And Mechanism For Sharing of Ists Charges and Losses
4. Principles for sharing ISTS charges and losses.
5. Mechanism to share ISTS transmission charges.
6. Mechanism of sharing of ISTS losses.
Chapter 4
Processes For Sharing of Transmission Charges and Losses
7. Process to determine Point of Connection Transmission Charges and Losses allocations.
8. Determination of specific transmission charges applicable for a Designated ISTS Customer.
9. Differentiation among various categories of transmission Designated ISTS Customers.
Chapter 5
Accounting, Billing and Collection of Charges
10. Accounting of charges.
11. Billing.
1. Point of Connection transmission charge towards LTA/MTOA. - For Generators having LTA to target region:
[PoC transmission rate of generation zone in Rs / MW / month] x[(Approved Injection)]For Demand:[PoC transmission rate for demand zone in Rs /MW /month] x[(Approved Withdrawal)]2. Reliability Support Charge. - For Generators having LTA to target region:
[Reliability Support Rate in Rs /MW /month] x[(Approved Injection)]For Demand:[Reliability support r ate in Rs /MW /month] x[(Approved Withdrawal)]3. HVDC charge. - (i) 10% of Monthly Transmission Charges (MTC) of HVDC transmission system shall form part of Reliability Support Charges and the balance shall be billed as detailed below:
Transmission charges for HVDC system created to supply power to specific regions shall be borne by DICs of such regions. The HVDC Charge shall be payable by DICs of the Region in proportion to their Approved Withdrawal. In case of Injection DICs having Long Term Access to target region, it shall also be payable in proportion to their Approved Injection.For Generators having LTA to target region:[HVDC Charge for Region in Rs/month] x [Approved Injection] / [Total Approved Withdrawal of the Withdrawal DIC and Approved Injection of the Generator having LTA to target Region]For Demand:[HVDC Charge for Region in Rs/month] x [Approved Withdrawal] / [Total Approved Withdrawal of the Withdrawal DIC and Approved Injection of the Generator having LTA to target Region](ii)HVDC Charge shall also be applicable for additional MTOA. Over/under recovery of HVDC charges shall be adjusted in the third part of bill in a manner as provided in Regulation 11(6) of these Regulations.(iii)Where transmission charges for any HVDC system are to be partly borne by a DIC (injecting DIC or withdrawal DIC, as the case may be) under a PPA or any other arrangement, transmission charges in proportion to the share of capacity in accordance with the PPA or other arrangement shall be borne by such DIC and the charges for balance capacity shall be borne by the remaining DICs by scaling up of MTC of the AC system included in the PoC. Such HVDC shall not be considered under (i) above.This first part of the bill shall be raised based on the Point of Connection rates, Reliability Support rate, HVDC Charge, Approved Withdrawal and Approved Injection for each DIC, provided by the Implementing Agency on the next working day of uploading of the Regional Transmission Accounts by the respective Regional Power Committees on their websites in each month for the previous month and determined prior to the commencement of the application period:Provided that the list of transmission assets along with the approved transmission charges for which billing has been done shall be enclosed with the first part of the bill:Provided further that the charges for the DICs having long term access without beneficiaries shall comprise the Injection POC Charges, Reliability Support Charges and HVDC Charges.] [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (15.6.2010).]1. [25× PoC Transmission Charge for the demand zone in Rs /MW / time block]×
[(Average MW Withdrawal during time blocks of such negative deviation)]For Demand:In case Average MW withdrawal during time block of positive deviation is greater the sum of Approved Withdrawal, Approved Additional Medium Term Withdrawal and Approved Short Term Withdrawal, then for the first 20% deviation, transmission charges shall be at the zonal Point of Connection charges for the demand zone.For deviation beyond 20%, the additional transmission charges shall be 1.25 times the zonal Point of Connection charges for the demand zone.In case a withdrawing DIC becomes a net injector the additional transmission charges shall be computed as[(Average MW Injected during time blocks of such negative deviation)]1. [25× PoC Transmission Charge for the generation zone in Rs /MW / time block]×
[This bill shall be raised by the CTU within 3 (three) working days of the issuance of the Regional Transmission Deviation Account by the RPCs:Provided that the agency of the State responsible for the intimation of deviation on account of Unscheduled Interchange energy shall be the agency responsible for the intimation of deviation on account of the transmission usage to the respective RPCs, for inclusion of the same in their Regional Transmission Deviation Account (RTDA):Provided further that the revenue collected against the Bill for Deviation from DICs in the synchronously connected grid shall be reimbursed to the DICs in the same synchronously connected grid having Long-term Access, in the following month, in proportion to the monthly billing of the respective month.] [Substituted by Notification No. L-1/44/2010-CERC, dated 24.11.2011 (w.e.f. 15.6.2010).][***] [Deleted '(8) Revenue from Approved Additional Medium term open access that was not considered in the Approved Injection / Approved Withdrawal shall be used for truing up the Yearly Transmission Charge for the next financial year' by Notification No. L-1/44/2010-CERC, dated 24.11.2011 (w.e.f. 15.6.2010).].12. Collection.
Chapter 6
Commercial Agreements
13. Transmission Service Agreement (TSA).
14. Amendment of existing contracts.
15. Transition Period/Mechanism.
Chapter 7
Information Procedures
16. Provision of information by Designated ISTS Customers and other constituents.
17. [ Information to be published by the Implementing Agency. [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).]
Chapter 8
Implementation Arrangements
18. Implementing Agency.
Chapter 9
Miscellaneous
19. Savings and Repeal.
20. Power to Relax.
21. Power to Remove Difficulties.
1. For every individual generator i, a number of physical paths are constructed, starting at the node where the producer injects the power into the grid, following through the lines as the power moves through the network, and finally reaching several of the loads in the system.
2. Similar calculations are also performed for the demands, tracing upstream the energy consumed by a certain user, from the demand bus until some generators are reached. One such physical path is constructed for every producer and for every demand.
3. In order to create such physical paths, a basic criterion is adopted: A rule allocates responsibility for the costs of actual flows on various lines from sources to sinks according to a simple allocation rule, in which inflows are distributed proportionally between the outflows. The main attractions of tracing are that the rule has some theoretical backing based and does not require the choice of a slack node. The drawbacks of tracing are first that aggregation of users can lead to counterintuitive results: if generation and load or different nodes are aggregated, then they are exposed to different tariffs. Second, the choice of the allocation rule is decisive but apparently arbitrary. An illustrative example of the proportional allocation mechanism is demonstrated in Fig.3 below.
Fig. 3: Average Participation MethodThe average participation method calculates the participation of agent i by tracking the influence in the network of a transit between node i and several ending nodes that result from the rules that conform the algorithm. In the example above, based on flow in the outgoing lines, the injection of 40MW (through the red line) is allocated to the outgoing lines in the proportion of the transfers from the two outgoing lines. Thus the outgoing line that transfers 30 MW (i.e, 30% of the total transfer out of the bus) is allocated 30% of the 40 MW injection from the red line, i.e., 12 MW. Similar allocations are made for the other flows as well.2. Pricing Mechanism Under Selected Framework. - As discussed in the previous sections, based on the review of the international experience, the literature and the Indian system, the Hybrid method - a hybrid of the Marginal and Average Participation Methods has been found to be most appropriate. The details of the hybrid method are discussed in sections below. Following steps shall be followed in the implementation of the Hybrid Methodology:
1. Data Acquisition
2. Computation of Load Flows on the Basic Network
3. Network Reduction
4. Identification of Slack Node(s)
5. Hybrid Methodology for the determination of transmission charges
6. Hybrid Methodology for the determination of transmission losses
7. Determination of Sharing of YTC and Losses
8. Creation of Zones
2. [1.1 Nodal Generation and Demand Information
Data Required for Annual process of determination of transmission charges based on Hybrid Methodology. - The DICs will provide forecast injection/withdrawal information {MW and MVAR (or an assumption about the power factor to be used)} at all the nodes or a group of nodes in a zone (identified a-priori by the Implementing Agency (IA) in the Network. "Typical" injection/withdrawal data based on maximum injection/withdrawal as defined in these regulations shall be provided to the Implementing Agency by the DICs for each of the application period.DICs shall also provide injection and withdrawal data for the corresponding quarter of last three years. The data provided by the DICs shall be as per the formats prepared by the IA and duly approved by the Commission under the relevant provisions of these Regulations.Information provided by the DICs shall be vetted by the Implementing Agency as per the provisions of the Regulations and Detailed procedure notified by Implementing Agency.Methodology for calculation of forecasted maximum generation/withdrawal of DICs for vetting by Implementing AgencyFor Demand data. - The projected maximum withdrawal figures provided by DICs will be vetted by Implementing Agency based on the following:a. Monthly peak demand met for each State/UT in the last 3 years for the period corresponding to the Application Period shall be considered.b. The average of monthly peak demand met for each State/UT in each of the last 3 years for the period corresponding to the Application Period shall be calculated.c. The average peak demand met for each State/UT for the Application Period shall be projected based on last 3 years average of monthly peak demand met figures.d. Similarly All India peak demand met in last 3 years shall be averaged for the period corresponding to the Application Period. This shall be projected for the ensuing Application Period. The projected peak demand of each State/UT thus arrived shall be normalized with the projected All-India peak demand met of the Application Period under consideration for the current year.For Generation Data:a. The projected maximum injection figures provided by DICs shall be vetted by the Implementing Agency based on average of monthly maximum injection in the last 3 years (based on actual metered data available from RLDCs) for the period corresponding to Application Period projected for the ensuing Application Period. Similarly maximum injection data (for last 3 years as well as projected for the ensuing quarter) for generators embedded within the State system shall be provided by respective SLDC. In case data is not provided by SLDC to the Implementing Agency, the maximum injection of the concerned State shall be taken as the difference between peak met and withdrawal from ISTS based on actual metered data (for the time block corresponding to the block in which peak met occurred).b. If sum of projected generation in the grid is more than sum of projected demand, the generation may be proportionately reduced to match sum of withdrawal data. If sum of projected generation in the grid is less than sum of projected demand, the demand may be proportionately reduced to match sum of generation.c. The peak demand met figures in respect of each State/UT and All India peak met shall be taken from the final/revised monthly power supply position published by CEA.d. The Implementing Agency shall finalize the data duly maintaining Load Generation balance.e. If the Validation Committee encounters any difficulty for validation of Approved Injection or Approved Withdrawal or any other data on account of non availability or partial availability of any information from the DICs, the Validation Committee may adopt such method as may be considered necessary consistent with the objectives of these regulations.f. The data as validated/adopted by the Validation Committee shall be final.]1. - Load bus
2. - Generator or plant bus
3. - Swing bus
4. - Isolated bus
GL - Shunt conductance, MW at 1.0 per unit voltageBL - Shunt susceptance, MVAR at 1.0 per unit voltage. (- = reactor)IA - Area numberVM - Voltage magnitude, per unitBASKV - Base voltage, KVZONE - Zone2. [1.3 [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).] The line-wise YTC of the entire network shall be provided by the Transmission Licensees. In case a line is likely to be commissioned during the Application Period, the data in respect of the same, along with the anticipated COD will be provided by the CTU/ Transmission Licensee to the Implementing Agency.
For the determination of the transmission charges based on Hybrid Methodology applicable in the next Application Period, all the above data shall be provided to the Implementing Agency as per the timelines specified by the Implementing Agency.Overall charges to be allocated among nodes shall be computed by adopting the YTC of transmission assets of the ISTS licensees, deemed ISTS licensees and owners of the non-ISTS lines which have been certified by the respective Regional Power Committee (RPC) for carrying inter-State power. The Yearly Transmission Charge, computed for assets at each voltage level and conductor configuration in accordance with the provisions of these regulations shall be calculated for each ISTS transmission licensee based on indicative cost provided by the Central Transmission Utility for different voltage levels and conductor configuration. The YTC for the RPC certified non-ISTS lines which carry inter-State power shall be approved by the Appropriate Commission.In case line-wise tariff for the RPC certified non-ISTS lines has not been specified by the Appropriate Commission, the tariff as computed for the relevant voltage level and conductor configuration shall be used. The methodology for computation of tariff of individual asset shall be similar to the methodology adopted for the ISTS transmission licensees and shall be based on ARR of the STU as approved by the respective State Commission.Certification of non-ISTS lines carrying inter-State power, which were not approved by the RPCs on the date of notification of the Central Electricity Regulatory Commission (Sharing of Transmission Charges and Losses) Regulations, 2009, shall be done on the basis of load flow studies. For this purpose, STU shall put up proposal to the respective RPC Secretariat for approval. RPC Secretariat, in consultation with RLDC, using WebNet Software would examine the proposal. The results of the load flow studies and participation factor indicating flow of Inter State power on these lines shall be used to compute the percentage of usage of these lines as inter State transmission. The software in the considered scenario will give percentage of usage of these lines by home State and other than home State. For testing the usage, tariff of similar ISTS line may be used. The tariff of the line will also be allocated by software to the home State and other than home State. Based on percentage usage of ISTS in base case, RPC will approve whether the particular State line is being used as ISTS or not. Concerned STU will submit asset-wise tariff. If asset wise tariff is not available, STU will file petition before the Commission for approval of tariff of such lines. The tariff in respect of these lines shall be computed based on Approved ARR and it shall be allocated to lines of different voltage levels and configurations on the basis of methodology which is being done for ISTS lines.] [Added by Notification No. L-1/44/2010-CERC, dated 14.12.2017 (w.e.f. 15.6.2010).]2. [2 Computation of Load Flows on the Basic Network. [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).] - The Implementing Agency shall run AC load flow on the Basic Network using the technical data obtained from the DICs, SLDCs, RLDCs and NLDC. The real power generation at the generator nodes in the Basic Network shall be based on maximum injection of the generators connected directly to the ISTS or the injection submitted by the DICs, where such nodes are embedded in the networks of the DIC. The demand at the load nodes shall be based on the maximum demand met of the DICs. In the case of an STU / SEB, the total injection at all the generator nodes owned by the STU/SEB shall be equal to the aggregate of injection of the entities connected in the state network. Similarly, the withdrawal at all the nodes owned by the SEB/STU shall be equal to withdrawal of all the entities connected in the SEB / STU network.
In the process of convergence of the Load Flow on the Basic Network, the IA may require to make certain adjustments in the load/generation at various buses to ensure load generation balance. Such load flow analysis shall be performed for all the network conditions as required by the Regulations in force. The entire process of formation of the Basic Network and convergence to load flows shall be validated by the Validation Committee.]2. [3 [Deleted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).] ***]
| 2.3 Computation: Reduction of the Indian Grid.- The determination of transmission charges based on Hybrid Methodology is required to be limited to the network owned, operated and maintained by the ISTS Licensees and those transmission licensees / SEBs whose assets have been certified by RPC as being used for interstate transmission. "Neat" truncation of the grid at the interface of the state and the central sector boundaries is not possible because all the assets of PGCIL are not interconnected by their own assets. Preparation of a cogent network therefore requires consideration of state owned lines also. One of the methods of network reduction, viz., network truncation is explained below. However IA may adopt alternative network reduction tools that find smaller but equivalent representations of large networks after due approval of the Commission.Most of the assets of PGCIL are operated at 400 kV. For the year 2008-09, PGCIL had Rupees 221 Crores (excluding NER) to be recovered from 220 kV assets of the total YTC of Rupees 4959.43 Crores. Most of the 220 kV assets in India are owned by the state utilities. It was, therefore, deemed appropriate by the CEA that the network be truncated at 400 kV level because it would involve minimal use of the state owned lines. The voltage level for the purposes of network truncation may be revised in the subsequent years by the IA after approval by the Commission.The complete Network shall be truncated at 400 kV level by the Implementing Agency following the following guidelines:1. The IA shall run AC Load Flow on the two grids - NEW Grid and SR Grid separately till these grids are synchronously integrated.2. Based on the load flow analysis on the Basic Network, for each 400 kV node (and 132 kV in the NER grid) in the NEW grid (except NER, where the network shall be truncated at 132 kV) and SR grid, the IA shall determine the net power flowing out of each node and power flowing into each node from the power system at lower voltage levels connected to this node, to compute the total injection and / or total withdrawal at each node from the lower voltage power system. a. All injection from the lower voltage system into 400 kV (in the case of NEW grid except NER and SR grid) and 132 kV in the case of NER grid shall be treated as a generator and vice-versa in the case of net withdrawal, the system below each node shall be replaced by a net demand.3. The network thus modified will have assets at 400 kV (and upto 132 kV assets in NER) and higher voltages with revised generation and load buses.4. A truncated network for each grid condition for each season shall be obtained based on the above guidelines.5. The Implementing Agency shall execute AC load flow on the truncated network and the truncation shall be accepted only when the (1) Slack bus generation, (2) Voltage angles at generation and demand buses closely match with the AC load flow on the full network.6. The network considered for NER region will however have all the assets from 765 kV to 132 kV.The truncated network so obtained shall be used for the implementation of the Marginal Participation methodology of transmission pricing. |
1. Marginal participation sensitivities are obtained that represents how much the flow through each network branch j increases when the injection/ withdrawal in a bus is increased by 1 MW. Flow variation in each network branch j incurred by 1 MW injection / withdrawal at each bus is computed for each scenario, e.
2. Due to the Kirchoff's laws, any 1 MW increase in generation (or load) at node i has to be compensated by a corresponding increase in load (or generation) at some other node or nodes (after adjusting for incremental system losses). Thus the calculation of how much an injection (or withdrawal) at a certain bus affects the flows in the network depends on the decision of which is the node that responds, and the answer that is demanded from the method is heavily conditioned by an assumption that it needs as an input. The methodology used for the selection of the distributed slack buses is explained above.
3. Once the flow variation in each line incurred by each agent and [***] [Deleted 'for every scenario' by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).] is obtained, it is possible to compute a seasonal usage index for each network user. This index is computed according to equation given below. It can be seen that only positive increments in the direction of the power flow in the base case are considered. This implies that increments which reduce burden on lines are neither given any credit nor charged for use of the system. This is essentially because of practical reasons where it could be difficult to pay grid connected entities for being connected to the grid. Further, there could be times (with strictly positive chance) when these entities need to use certain network branches along the direction of the main flow, though such times may not be the times which coincide with [maximum injection/ maximum withdrawal] [Substituted 'typical seasonal system peak and other than peak periods' by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).] considered in the load flow studies. This is also a standard international practice followed in countries where such pricing mechanisms are used.
The [***] [Deleted 'seasonal' by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).] index (for each block of months) is computed as:Ue,i,l = (| F le i | - | F le |).Pie.| F le i | - | F le | > 0,Sign (F le i) is same as Sign (F le )Where,Ueil is the [***] [Deleted 'seasonal' by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).] usage index in line l due to injection / withdrawal at node iFle is the flow in line l under scenario e under base caseFi le is the flow in line l under scenario e due to injection / withdrawal of 1 MW at nodePie is power dispatch / demand at bus i under scenario e under base case4. The revenue requirement of each line is allocated pro-rata to the different agents according to their total participation in the corresponding line.
| Cost Allocatedeil=| Ueil∑ Ueil| ×| C1 |
| | Ueil∑ Ueil| ×| is the marginal participation factor |
| | | Marginal Loss Factori=| ∂ System Losses∂ Power generation / load at Node i| ki| |
2. The selection of the slack buses for absorption (supply) of the incremental injection (withdrawal) is done as per the methodology discussed above.
3. The marginal loss factors are multiplied by the generation / demand at these nodes under base case, i.e.
K i× P ig for generation nodesK j× Pdj for demand nodesPi g is base case generation at node iWhere,Pi d is base case demand at node j4. Loss Allocation Factor for generation and demand nodes are computed by:
| | ki× Pig∑ ki× Pig+ ∑ kj× Pjd| for generation node i and |
| | kj× Pjd∑ ki× Pig+ ∑ kj× Pjd| for demand node j |
5. The Loss Allocators computed above are multiplied by the total system losses to allocate losses to each node in the system.
1. [ Converged AC Load Flow data for the all India Grid shall be used directly for the implementation of the Hybrid Methodology. [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).]
2. Treatment of HVDC: Flow on HVDC systems is regulated by power order and remains constant for marginal change in load or generation. Hence, marginal participation (MP) of HVDC systems is zero. Since the HVDC systems were specifically set up for transfer of bulk power to specific Region, the DICs of the Region shall share the cost of HVDC systems. HVDC system also helps in controlling voltages and power flow in inter-regional lines and some benefits accrue to all DICs by virtue of HVDC system. Accordingly, 10 % of the MTC of these systems be recovered through Reliability Support Charges. The balance amount shall be payable by Withdrawal DICs of the Region in proportion to their Approved Withdrawal. In case of Injection DICs having Long Term Access to target region, it shall be payable in proportion to their Approved Injection.
Where transmission charges for any HVDC system line are to be partly borne by a DIC (injecting DIC or withdrawal DIC, as the case may be) under a PPA or any other arrangement, transmission charges in proportion to the share of capacity in accordance with PPA or other arrangement shall be borne by such DIC and the charges for balance capacity shall be borne by the remaining DICs by scaling up of YTC of the AC system included in the PoC.]3. Using AC load flow, marginal participation factors shall be computed for determination of transmission system utilization due to marginal injection / withdrawal at each generator / demand node.
4. YTC for each line shall be based on the line-wise YTC provided by the Transmission Licensees. Average per km YTC for each voltage level (and line configuration viz., 400 KV D/C twin Moose, 400 kV Quad Moose, 400 kV Quad Bersimis etc.) of the transmission licensee lines shall be applied to the 765 kV, 400 kV, 220 kV and 132 kV lines considered in the network.
5. [ Hybrid Methodology shall be applied to Application Period. [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).]
6. Annual Average YTC of each line will then be attributed to maximum injection/maximum withdrawal.]
7. The annual average YTC (of each period in each season) of each line is attributed to the total change in flow in each line. Therefore the YTC is allocated to each agent in proportion of the change in the flow in network branch affected by that agent.
8. Transmission charges based on Hybrid Methodology in Rs/MW/Month and Rs/MW/hr at each node in each block of months will be computed.
9. Loss Allocators shall also be computed along with the above simulations and as discussed above.
10. Total losses shall be computed, as per the present methodology, viz.,
The total net drawal by each utility is subtracted from the sum of net injection of Inter-State Generating Stations (ISGS) and the inter-regional injections to arrive at the losses in MWh.All loss computations are on a weekly basis from the Special Energy Meters (SEMs) installed at all inter-utility exchange points in the region. A week for the purpose of accounting is from 0000 hours of Monday to 2400 hours of the following Sunday.11. Using the loss allocators, the losses shall be allocated to each node, as per the detailed procedure to be developed by NLDC under these Regulations.
12. [ There shall be slabs for the percentage transmission losses in the All India grid till such period the Commission may consider appropriate.] [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).]
| Node | Transmission Charges | Approved Injection/ Withdrawal* | Zonal Transmission Rate |
| (`/Month) | (MW) | (`/MW/Month) | |
| PP | 45,00,000 | 250 | 70000 |
| AA | 50,00,000 | ||
| KK | 80,00,000 | ||
| ZZ - ZONE | 1,75,00,000 | 250 |