State of Himachal Pradesh - Subsection

Section 23(3)(i) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

(i)if the equity actually deployed is more than 30% of the capital cost admitted by the Commission under regulation 15, the equity deployed in excess of 30% limit shall be treated as normative loan in accordance with the National Tariff Policy and shall be deemed as advanced at the weighted average rate of interest and for a weighted average tenor of the long term debt component of the project after ascertaining the reasonableness of the interest rates and taking into account the effect of debt restructuring, if any;