State of Himachal Pradesh - Act
Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017
HIMACHAL PRADESH
India
India
Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017
Rule HIMACHAL-PRADESH-ELECTRICITY-REGULATORY-COMMISSION-PROMOTION-OF-GENERATION-FROM-THE-RENEWABLE-ENERGY-SOURCES-AND-TERMS-AND-CONDITIONS-FOR-TARIFF-DETERMINATION-REGULATIONS-2017 of 2017
- Published on 16 November 2017
- Commenced on 16 November 2017
- [This is the version of this document from 16 November 2017.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title and commencement.
2. Definitions and Interpretation.
| (a) Wind energy power project | 25 years |
| (b) Biomas power project, non-fossil fuel basedcogeneration | 20 years |
| (c) SHPs | 40 years |
| (d) Municipal Solid Waste (MSW)/ Refuse DerivedFuel (RDF) based power project | 20 years |
| (e) Solar PV/Solar thermal power plant | 25 years |
| (f) Any other renewable energy technologyapproved by the MNRE; | As may be fixed under regulation 18 |
3. Scope and extent of application.
4. Eligibility Criteria.
- A project shall be eligible for being considered to be based on renewable sources of energy on the fulfilment of the following criteria:-5. Promotion of renewable energy sources.
6. Grid Connectivity.
- Mechanism for grid connectivity shall be as under-7. Coordination Committee.
- The Commission may constitute a coordination committee to facilitate coordination among the State Transmission Utility, transmission licensee, distribution licensee, HIMURJA and Directorate of Energy of the State Government for evacuating power from renewable energy projects.Chapter-III Tariff Determination General Principles8. Power Purchase Agreement.
9. Control period or review period.
- [(1) The Commission shall fix the durations of the control period(s) for the respective Renewable Energy Technologies under these regulations from time to time:Provided that the first control period for the small hydro projects under these Regulations shall start from the 1st October, 2017 and shall end on the 30th September, 2019:Provided further that the technology specific parameters for the renewable energy sources, other than small hydro projects, may be fixed for such durations and reviewed at such intervals, as the Commission may find appropriate in accordance with Regulation 18.] [Substituted by Notification No. No. HPERC/428, dated 28.1.2019.]10. Tariff period.
- The duration of tariff period in case of small hydro projects shall be 40 years and for other renewable technologies, the Commission may fix the same under regulation 18.11. [ [Omitted by Notification No. No. HPERC/428, dated 28.1.2019.]
***]| 11. Special provisions for Small Hydro Projects.- (1) Where the first Implementation Agreement of a small hydro project has been executed on or before 31st December, 2014 and neither any joint petition for approval of the Power Purchase Agreement has been filed before, nor any power purchase agreement, whether under REC Mechanism or otherwise, has been approved by, the Commission for such project prior to the date of commencement of these Regulations, the norms, tariffs and other associated terms and conditions as per Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012, shall be applicable in the same manner as applicable to the small hydro projects covered in the said Regulations:Provided that for the purpose of this regulation, the date of signing the first Implementation Agreement of the small hydro project shall only be taken into account and the Supplementary Agreement(s), if any, executed thereafter due to any reason, but other than due to enhancement of capacity, whatsoever, viz for extension of the scheduled completion date, shall not be considered:Provided further that in cases where the power purchase agreements have already been approved by, or the joint petitions for approval of the power purchase agreement(s) have been filed before, the Commission prior to the date of commencement of these Regulations, the tariff(s) for such small hydro projects shall be governed as per the provisions of power purchase agreements and relevant Regulations irrespective of the dates on which such agreement(s) are actually approved and/or executed:Provided further that if a Supplementary Implementation Agreement is executed on or after 1st January, 2015 to provide for enhancement of capacity, the tariff and other terms and conditions as per regulation 14 and regulations 20 to 41 shall be applicable only for the incremental energy generation as per the provisions under regulations 17.(2) Save as provided in sub-regulation(1), the tariff determined under the regulation 14 and regulations 20 to 41 shall be applicable only for such small hydro projects where-(i) the 1st Implementation Agreement has been signed on or after 1st January, 2015;(ii) no power purchase agreement, whether under REC Mechanism or otherwise, has been approved by the Commission before the date of commencement of these Regulations; and(iii) the RE generator implementing the small hydro project has neither filed joint petition for approval of PPA before the Commission, nor has commenced the operation of its project, prior to the date of commencement of these Regulations. |
12. Tariff design.
13. Tariff options/applicability.
14. [ Generic levellised tariff. [Substituted by Notification No. No. HPERC/428, dated 28.1.2019.]
15. Project specific levellised tariff.
16. Tariff for residual period after sale/purchase under REC mechanism.
17. Capacity enhancement.
| A | if no separate rates of free power (inpercentage) are provided in supplementary IA for the originalcapacity and for the additional capacity and only composite rateis provided for the enhanced capacity; | composite rate of free power (in percentage),not exceeding the limits specified in regulation 36, for theentire capacity i.e. in relation to the original capacity as wellas additional capacity; |
| B | if separate rates for original capacity and forthe additional capacity are provided in the supplementaryImplementation Agreement; | Separate adjustments in accordance with thelimits specified in regulation 36 shall be made for the netsaleable energy in relation to the two capacities i.e. originalcapacity and additional capacity at corresponding rates of freepower (in percentage). In such cases the limits as per regulation36 shall be applicable separately for the two capacities: |
18. Tariff for renewable energy projects, other than small hydro projects.
19. Petition and proceedings for determination of project specific levellised tariff.
20. Review of tarif.
21. Capital Cost.
22. Subsidy or incentive or grant/budgetary support by the Central/State Government.
23. Debt-Equity Ratio.
24. Loan and Finance Charges.
25. Depreciation.
- For the purpose of tariff determination, depreciation shall be computed in the following manner, namely:-26. Return on Equity.
27. Interest on working capital.
28. Operation and maintenance expenses.
29. Taxes and duties.
- Tariff determined under these Regulations shall be inclusive of all taxes and duties and shall not be subject to any change except for the provisions specified under regulation 20.30. Rebate.
31. Late payment surcharge.
- The distribution licensee shall make timely payments of energy bills of the renewable energy generators by assigning priority over and above all other payments. In case the payment of any bill for charges payable under these Regulations is delayed beyond a period of 60 days from the date of billing, a late payment surcharge at the simple interest rate of 1.25% per month shall be levied by the renewable energy generator for the actual number of days by which the payment is delayed.32. Ceiling norms.
- The financial norms, except for capital cost, as specified in this Chapter of these Regulations, shall be considered as ceiling norms and the same shall not preclude the licensee or renewable energy generator from agreeing to improved norms, including operation and maintenance norms, which may lead to overall reduction in the levellised tariff and in case the improved norms are agreed to, such improved norms shall be applicable for determination of the project specific levellised tariff.Chapter-V [Technology Specific Parameters for Small Hydro Projects] [Substituted by Notification No. No. HPERC/428, dated 28.1.2019.]33. Categorisation.
- For the purpose of tariff determination, the small hydro projects shall be categorized as under:-| (i) | Above 100 kW to 2 MW capacity |
| (ii) | Above 2 MW to 5 MW capacity |
| (iii) | Above 5 MW to 25 MW capacity |
34. Normative Capital cost.
| Sr. No. | Category of small hydro project | Rupees in Lac per MW |
| (i) | Above 100 kW to 2 MW capacity | 880 |
| (ii) | Above 2 MW to 5 MW capacity | 850 |
| (iii) | Above 5 MW to 25 MW capacity | 800 |
35. Normative saleable energy.
36. Free Power.
| Rate payable for the month for the net saleableEnergy (Rs/kWh) | = a x (100-b)/(100-c) |
37. Auxiliary consumption and transformation losses.
- Normative auxiliary consumption and transformation losses for the small hydro projects shall be 0.5% of the gross generation and the same for transformation losses at the switchyard linked to the generating station of the projects shall also be 0.5%:Provided that for the sake of simplicity, these two factors shall be clubbed together and accounted for as 1% of the gross generation.38. Energy losses.
39. Operation and maintenance expenses.
| Sr. No. | Category of Project | Annual O&M expenses Rupees in Lac per MW |
| (i) | Above 100 kW to 2 MW capacity | 33 |
| (ii) | Above 2 MW to 5 MW capacity | 29 |
| (iii) | Above 5 MW to 25 MW capacity | 24 |