State of Rajasthan - Subsection
Section 40(2) in Rajasthan Transparency in Public Procurement Rules, 2013
| S. No. | Authority competent to take decision | Time allowed for decision |
| 1 | 2 | 3 |
| 1. | Head of Office or Executive Engineer | Twenty days |
| 2. | Regional Officer or Superintending Engineer | Thirty Days |
| 3. | Head of the Department or Chief Engineer/Additional Chief Engineer | Forty days |
| 4. | Administrative Department concerned/Finance Committee/ Board/Empowered Committee/Empowered Board etc. | Fifty days |