State of Rajasthan - Act
Rajasthan Transparency in Public Procurement Rules, 2013
RAJASTHAN
India
India
Rajasthan Transparency in Public Procurement Rules, 2013
Rule RAJASTHAN-TRANSPARENCY-IN-PUBLIC-PROCUREMENT-RULES-2013 of 2013
- Published on 24 January 2013
- Commenced on 24 January 2013
- [This is the version of this document from 24 January 2013.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title and commencement.
2. Definitions.
3. Procurement committees.
4. State Public Procurement Portal.
- The State Public Procurement Portal, in addition to information specified in clause (a) to (g) of sub-section (3) of section 17, shall provide access to such other information as may be specified by the State Government, from time to time. Every procuring entity shall upload and publish the required information on State Public Procurement Portal maintained by the State Procurement Facilitation Cell.5. e-procurement.
- All subject matters of procurement of an estimated value, as may be notified by the State Government under sub-section (2) of section 28, shall be procured through e-procurement. In such cases every bidder shall deposit user charges as may be fixed by the State Government, from time to time. Every bid shall be digitally singed by the bidder. The procedure of e-procurement shall be as specified for this purpose on the State Public Procurement Portal.Chapter- III General principles of procurement6. Determination of need.
- In every case of a procurement, the procuring entity shall first determine the need and maintain documents relating to determination and assessment of need in accordance with the provisions of section 5.7. Procurement plan.
8. Numbering convention.
- Each procurement process undertaken by any procuring entity shall have a Unique Bid Number which shall be used for tracking purpose during and after the bid process. The Unique Bid Number shall be designed like a code to reflect department/Procuring Entity, type of procurement, threshold value of procurement and method, year and serial number of bid in that particular year.9. Procurement Management Information System and tracking.
- Every procuring entity shall develop and maintain a Procurement Management Information System for tracking the procurement process, which shall include the following, namely:-10. Procurement Register.
- Each procuring entity shall maintain a procurement register and ensure the safe custody of the procurement register.11. Administrative, Financial and Technical sanctions and availability of budget provision.
- For each procurement, it shall be necessary to obtain all required approvals and sanctions as applicable. In case of procurement of works, this shall include administrative sanction, financial sanction, technical sanction and appropriation or re-appropriation. The procuring entity must have the necessary financial powers delegated to it for procurement of the subject matter.12. Obligations related to value of procurement.
- The obligations related to value of procurement shall be as per the provisions of section 8.13. Participation of bidders.
14. Methods of Procurement.
- Subject to the provisions of the Act, these rules, any additional conditions notified under section 37 and guidelines issued under the Act, a procuring entity may procure a subject matter of procurement by any of the methods specified or notified under sub-section (1) of section 28.15. Open competitive bidding.
- Procedure for procurement of a subject matter through open competitive bidding shall be as specified in Chapter-V of these rules.15A. [ Swiss Challenge Method. [Inserted by Rajasthan Notification No. G.S.R. 37, dated 5.6.2015 (w.e.f. 24.1.2013).]
- Procedure for procurement of a subject matter through Swiss Challenge Method shall be as specified in Chapter-VA of these rules.]16. Limited bidding.
17. Single source procurement.
18. Two stage bidding.
- The procedure for two stage bidding shall be as under :-19. Procedure of electronic reverse auction.
20. Registration for the electronic reverse auction and the timing of holding the auction.
21. Requirements during the electronic reverse auction.
22. Requirements after the electronic reverse auction.
23. Other provisions for electronic reverse auction.
- Except as otherwise provided in rule 19 to 22, the provisions of Chapter-V shall, mutatis mutandis, apply to electronic reverse auction, except rules 40, 49, 50, 52, 64, 68 and 69.24. Request for Quotations.
25. Spot Purchase.
26. Procurement without quotations.
- The subject matter of procurement valuing up to rupees ten thousand may be procured on one occasion subject to a limit of below rupees one lakh during a financial year without inviting quotations, from the Government Departments/Corporations, authorised dealers, cooperative stores/bhandars or retailers who are bona-fide dealers in the subject matter of procurement.27. Procurement of works by work order system and piece work system.
28. Competitive negotiations.
- The procedure for competitive negotiation shall be as under :-29. Rate contract.
30. Registration.
- The registration of the bidders shall be carried out in the manner and in accordance with the rules made in this behalf by the State Government.31. Empanelment by pre-qualification process.
32. Direct procurement from notified agencies.
- A procuring entity may procure subject matter of procurement from the category of bidders, without inviting bids, as notified by the State Government, from time to time.33. Purchase or price preference in procurement.
- A procuring entity shall provide price preference or purchase preference in procurement, to the category of bidders as notified by the State Government, from time to time.Chapter- V Bid Process Management- Open Competitive Bidding34. Description of subject matter of procurement.
35. Criteria for evaluation of bids.
- In addition to the criteria for evaluation set out in section 14, the evaluation criteria, where relevant, may include the discounted cash flow techniques.36. Preparation of bidding documents.
37. Single part and two part bids.
- A procuring entity may choose to invite bids in one part or two parts, as per the provisions of section 13.38. Qualification of bidders.
- In addition to the provisions regarding qualification of bidders as set out in section 7, -39. Eligibility of bidders.
40. [ Time frame for procurement process. [Substituted by Notification No. S.O. 119, dated 6.8.2018 (w.e.f. 24.1.2013).]
| S. No. | Stages ofProcurement | Procurement Method | |
| Open Competitive Bidding | Limited Bidding and Single Source Procurement | ||
| 1 | 2 | 3 | 4 |
| 1. | Issue of bidding documents | On the day of first publication of NoticeInviting Bids. | - |
| 2. | Submission of bids | (i) Thirty Days, if estimated value of procurement is more than Rs. 50 crores and Twenty days, if the estimated value of procurement is upto Rs. 50 crores from the date of first publication of Notice Inviting Bids.(ii) Where clarifications/ addendum are issued, at least fifteen days, if estimated value of procurement is more than Rs. 50 crores and 10 days, if estimated value of procurement is upto Rs. 50 crores, from the date of issue of clarifications/ addendum:(iii) In case of International Competitive Bidding, the period of submission of bids shall be forty five days from the date of first publication of Notice Inviting Bids and at lest twenty days from the date of issue of clarifications/ addendum. | Seven days from issue of Bidding documents/dateof issue of clarifications/addendum. |
| 3. | Technical bid opening | Within one day of last day of submission ofbids. | Within one day of last day of submission ofbids. |
| 4. | Issue of letter of award | Within three days of approval of award by thecompetent authority. | Within three days of approval of award by thecompetent authority. |
| 5. | Execution of contract agreement | Within fifteen days of issue of letter of awardor a period as specified in the bidding documents. | Within fifteen days of issue of letter of awardor a period as specified in the bidding documents. |
| 6. | Declaration of the bid results on State PublicProcurement Portal and Procuring entity's website, if any | Within three days of issue of letter ofacceptance. | Within three days of issue of letter ofacceptance. |
| S. No. | Authority competent to take decision | Time allowed for decision |
| 1 | 2 | 3 |
| 1. | Head of Office or Executive Engineer | Twenty days |
| 2. | Regional Officer or Superintending Engineer | Thirty Days |
| 3. | Head of the Department or Chief Engineer/Additional Chief Engineer | Forty days |
| 4. | Administrative Department concerned/Finance Committee/ Board/Empowered Committee/Empowered Board etc. | Fifty days |
41. Pre-qualification proceedings.
- In addition to the provisions of section 18 the procedure of pre-qualification process shall be carried out in the manner as specified below-42. Bid security.
43. Notice Inviting Bids.
| S. No. | Estimated value of procurement | Period for submission of bid from the date offirst publication of Notice Inviting Bid | Mode of publication | |
| 1 | 2 | 3 | 4 | |
| 1. | Up to rupees ten lakh | Seven days | (i)(ii) | Notice Board of the procuringentity and all subordinate Regional and Divisional Head Quarters, as thecase may be.One Regional daily newspaper. |
| 2. | Above rupees ten lakh and upto Rupees one Crore | Ten days | (i)(ii)(iii) | Notice Board of theprocuring entity and all subordinate Regional and Divisional HeadQuarters, as the case may be.One Regional dailynewspaper.One leading daily State Level newspaper havingcirculation of fifty thousand copies and above. |
| 3. | Above rupees one crore | Twenty days | (i)(ii)(iii) | Notice Board of theprocuring entity and of all subordinate Regional and DivisionalHead Quarters, as the case may be.One State levelleading daily newspaper having circulation of fifty thousandcopies and aboveOne all India level English daily newspaper with widecirculation. |
| S. No. | Estimated Value of procurement | Period for submission of bid from the date offirst publication of Notice Inviting Bid | Mode of publication | |
| 1 | 2 | 3 | 4 | |
| 1. | Up to rupees ten lakh | Seven days | (i)(ii) | Notice Board of the procuring entity and itssubordinate offices; andOne leading Regional daily newspaper. |
| 2. | Above rupees ten lakh and upto Rupees two crore | Ten days | (i)(ii) | Notice Board of theprocuring entity and its subordinate offices, andOne leading Regional daily newspaper and one Statelevel leading daily newspaper having circulation of 50,000 copies or more. |
| 3. | Above rupees two crore and upto 50 crore | Twenty days | (i)(ii)(iii) | Notice Board of theprocuring entity and its subordinate offices.One leading Regional daily newspaper and one State level leading daily newspaper having circulation of 50,000 copies or more, andOne all India level daily English newspaper with wide circulation. |
| 4. | Above rupees 50 crore | Thirty days | (i)(ii)(iii) | Notice Board of theprocuring entity and its subordinate offices.One leading Regionaldaily newspaper, one State level leading daily newspapers havingcirculation of 50,000 copies or more.One all India level daily newspaper with widecirculation. |
44. Price for bidding documents, pre-qualification documents or bidder registration documents and processing fee or user charges.
- The price for the bidding documents, pre-qualification documents or registration documents shall be fixed after considering its preparation and delivering costs. The procuring entity may also charge processing fee or user charges for using e-procurement facility.45. Sale of bidding documents
46. Pre-bid clarifications.
- Subject to the provisions contained in section 22, the procuring entity ma y convene a pre-bid conference of the bidders and shall prepare minutes of the meeting containing the requests submitted at the meeting for clarification of the bidding documents and its responses to those requests, without identifying the person, who made the requests. The minutes and response under sub-section (3) of section 22, if any, shall be provided promptly to all bidders to which the procuring entity provided the bidding documents, so as to enable those bidders to take the minutes into account in preparing their bids, and shall be published on the State Public Procurement Portal.47. Changes in the bidding documents.
- At any time prior to the deadline for presenting bids, the procuring entity may for any reason, whether on its own initiative or as a result of a request for clarification by a bidder, modify the bidding documents by issuing an addendum in accordance with provisions of section 23.48. Period of validity of bids.
49. Format and signing of bids.
50. Sealing and marking of bids.
51. Deadline for the submission of bids.
52. Late bids.
- The person authorised to receive the bids shall not receive any bid that is submitted personally, after the time and date fixed for submission of bids. Any bid which arrives by post after the deadline for submission of bids shall be declared and marked as "Late" and returned unopened to the bidder by registered post.53. Receipt and Custody of Bids.
54. Withdrawal, substitution and modification of bids.
55. Opening of bids.
56. Preliminary examination of bids.
- The bid evaluation committee constituted by the procuring entity shall conduct a preliminary scrutiny of the opened bids to assess the prima-facie responsiveness and ensure that the-57. Tabulation of Technical bids.
58. Tabulation of Financial bids.
59. Determination of responsiveness.
60. Clarification of bids.
61. Non-material Non-conformities in bids.
62. Exclusion of bids.
- A procuring entity shall exclude a bid in accordance with the provisions of section 25.63. Evaluation of Technical bids in case of two part bids.
64. Correction of arithmetic errors in financial bids.
- The bid evaluation committee shall correct arithmetical errors in substantially responsive bids, on the following basis, namely :-65. Evaluation of financial bids.
- Subject to the provisions of section 27, the procuring entity shall take following actions for evaluation of financial bids :-66. Comparison of rates of firms outside and those in Rajasthan.
- While tabulating the bids of those firms which are not entitled to price preference, the element of Rajasthan Value Added Tax shall be excluded from the rates quoted by the firms of Rajasthan and the element of Central Sales Tax shall be included in the rates of firms from outside Rajasthan for evaluation purpose.67. Price/purchase preference in evaluation.
- Price and/or purchase preference notified by the State Government and as mentioned in the bidding documents shall be considered in the evaluation of bids and award of contract.68. Lack of competition.
69. Negotiations.
70. Acceptance of the successful bid and award of contract.
71. Information and publication of award.
- Information of award of contract shall be communicated to all participating bidders and published on the State Public Procurement Portal in accordance with provisions of sub-section (3) of section 27.72. Procuring entity's right to accept or reject any or all bids.
- The Procuring entity reserves the right to accept or reject any bid, and to annul the bidding process and reject all bids at any time prior to award of contract, without thereby incurring any liability to the bidders. Reasons for doing so shall be recorded in writing.73. Right to vary quantity.
- Deleted74. Dividing quantities among more than one bidder at the time of award.
- As a general rule all the quantities of the subject matter of procurement shall be procured from the bidder, whose bid is accepted. However, when it is considered that the quantity of the subject matter of procurement to be procured is very large and it may not be in the capacity of the bidder, whose bid is accepted, to deliver the entire quantity or when it is considered that the subject matter of procurement to be procured is of critical and vital nature, in such cases, the quantity may be divided between the bidder, whose bid is accepted and the second lowest bidder or even more bidders in that order, in a fair, transparent and equitable manner at the rates of the bidder, whose bid is accepted if such condition is specified in the bidding documents. Counter offer to first lowest bidder (L1), in order to arrive at an acceptable price, shall amount to negotiation. However, any counter offer thereafter to second lowest bidder (L2), third lowest bidder (L3) etc., (at the rates accepted by L1) in case of splitting of quantities, as pre- disclosed in the bidding documents, shall not be deemed to be a negotiation.75. Performance security.
- [(1) Performance security shall be solicited from all successful bidders except the,-(i)Departments/Boards of the State Government or Central Government;(ii)Government Companies as defined in clause (45) of Sec. 2 of the Companies Act, 2013;(iii)company owned or controlled, directly or indirectly, by the Central Government, or by any State Government or Governments, or partly by the Central Government and partly by one or more State Governments which is subject to audit by the Auditor appointed by the Comptroller and Auditor-General of India under sub-section (5) or (7) of Sec. 139 of the Companies Act, 2013; or(iv)Autonomous bodies, Registered Societies, Cooperative Societies which are owned or controlled- or managed by the State Government or Central Government.However, a performance security declaration shall be taken from them. The State Government may relax the provision of performance security in a particular procurement or any class of procurement.] [Substituted by Notification No. S.O. 119, dated 6.8.2018 (w.e.f. 24.1.2013).]76. Execution of agreement.
77. Confidentiality.
- In addition to the restrictions specified in section 49, the procuring entity, while procuring a subject matter of such nature which requires the procuring entity to maintain confidentiality, may impose condition for protecting confidentiality of such information.78. Cancellation of procurement process.
- If any procurement process has been cancelled, it shall not be reopened but it shall not prevent the procuring entity from initiating a new procurement process for the same subject matter of procurement, if required.79. Documentary record of procurement proceedings.
79A. Swiss Challenge Method of Procurement.
- The Swiss Challenge Method is a method in which an unsolicited proposal for a government project is received and allows third party to challenge the original proposal through open bidding, and then lets the original proponent counter-match the most advantageous / most competitive offer.79B. Eligible sectors under Swiss Challenge Method.
- In following sectors Swiss Challenge Method of procurement may be adopted, namely: -79C. Projects, which shall not be acceptable under Swiss Challenge Method.
- The following proposals shall not be acceptable under Swiss Challenge Method, namely: -79D. Procedure.
79E. Preparation and submission of detailed and comprehensive proposal.
79F. Earnest Security.
79G. Detailed Project Report (DPR) preparation cost.
79H. Clarifications regarding Detailed Project Report (DPR).
- No changes shall be permitted in the DPR once the Project Proponent has submitted the DPR to the Administrative Department concerned. However, the Administrative Department may seek clarifications with respect to the DPR from the Project Proponent and these clarifications shall be attached as an addendum to the DPR.79I. Bid Parameters and Bid Value.
79J. Competent Authority for approval of Projects under SCM and Procedure to be followed thereof.
79K. Bidding Process.
79L. Transaction Advisor.
79M. Time frame for the total process.
- The time frame for procurement, through Swiss Challenge Method shall be as under: -| S. No. | Activity | Time Required |
| 1. | Examination of preliminary report and permissionto the proponent to proceed for preparation of detailed proposalOR rejection of the proposal, as the case may be, by theAdministrative Department. | One Month from the date of receipt of theproposal. |
| 2. | Detailed proposal submission by the proponent. | Within three Months or period extended undersub-rule (6) of Rule 79-D. |
| 3. | Examination of detailed proposal, preparation ofbid documents and approval from competent authority | Forty Five days |
| 4. | Bid invitation and submission of bids | (i) Thirty days from the date of firstpublication of Notice Inviting Bids; |
| (ii) Where clarifications/addendum are issued,at least Fifteen days from date of issue of clarifications/addendum; or | ||
| (iii) In case of International CompetitiveBidding, the period of submission of bids shall be forty fivedays from the date of first publication of Notice Inviting Bidsand at least twenty days from the date of issue ofclarifications/ addendum. | ||
| 5. | Bids evaluation | Fifteen Days |
| 6. | Time for project proponent to match the mostadvantageous bid, if any. | Fifteen Days |
| 7. | Letter of Award | Within 7 days of approval of award by thecompetent authority. |
| 8. | Execution of Contract Agreement | Within fifteen days of issue of letter of awardor a period as specified in the bidding documents. |
79N. Eligibility criteria for the Project Proponent.
79O. Power to call off the Project.
- The Administrative Department concerned shall have the right to call off the project anytime during the process without assigning any reason to the Project Proponent, but it may call off the project before entering into an agreement with the Project Proponent or the successful bidder, as the case may be. Once an agreement is entered in to by the Administrative Department concerned, the respective clauses of the duly entered agreement shall apply. If the Administrative Department calls off the project in the manner as specified above, the same shall be exhibit by the Administrative Department on State Public Procurement Portal.Chapter VI
Code of Integrity
80. Code of integrity.
81. Conflict of interest.
82. Breach of code of integrity by the bidder.
- Without prejudice to the provisions of Chapter IV of the Act, in case of breach of any provision of the code of integrity by a bidder or prospective bidder, as the case may be, the procuring entity may take appropriate action in accordance with the provisions of subsection (3) of section 11 and section 46.CHAPTER-VII Appeals83. Form of Appeal.
84. Fee for filing appeal.
85. Procedure for disposal of appeal.
86. Repeal and savings.
- All rules, regulations, orders, notifications, departmental codes, manuals, by-laws, official memoranda or circulars relating to procurement of goods, services or works provided for in these rules, which are in force on the date of commencement of these rules, in relation to the matter covered by these rules are hereby repealed to the extent they are covered by these rules:Provided that such repeal shall not affect the previous operation of rules, regulations, orders, notifications, departmental codes, manuals, by-laws, official memoranda or circulars, so repealed and the procurement process commenced before the commencement of these rules shall continue as per the provisions of rules, regulations, orders, notifications, departmental codes, manuals, by-laws, official memoranda or circulars, so repealed.Form No. 1[See rule 83]Memorandum of Appeal under the Rajasthan Transparency in Public Procurement Act, 2012Appeal No .........of ...............Before the ..............................(First/Second Appellate Authority)1. Particulars of appellant:
2. Name and address of the respondent(s):
4. If the Appellant proposes to be represented by a representative, the name and postal address of the representative:
5. Number of affidavits and documents enclosed with the appeal:
6. Grounds of appeal: ..................................................................................................................................................................
..................................................................................................................................................................................................................................................................................................................................................................................................................(Supported by an affidavit)7. Prayer: ..................................................................................................................................................................
..........................................................................................................................................................................................................................................................................................................................................................Place ...........................................Date ..........................................Appellant's Signature[Form No. 2] [Added by Rajasthan Notification No. G.S.R. 37, dated 5.6.2015 (w.e.f. 24.1.2013).][See Rule 79-D]Certificate to be furnished by Project ProponentIt is hereby certified that:1. The_____________________(Name of project) has been submitted by the undersigned as the duly authorised representative of_____________________(Name of Project Proponent) under the Swiss Challenge Method.
2. The Project Proponent will support fair competition through open bidding process to obtain the most advantageous bid.
3. The Project Proponent agrees to the standard project structure, bidding documents, concession agreement similar to other projects in the sector as decided by the Administrative Department / Government of Rajasthan.
4. The Project Proponent agrees to abide by the Regulatory Authority, as and when formed by the Government of Rajasthan or through law.
5. The Project Proponent agrees that the cost of preparation of DPR, as decided by the Administrative Department, shall be reimbursable to the project proponent as provided in Rajasthan Transparency in Public Procurement Rules, 2013.
6. The Project Proponent agrees that the Administrative Department concerned has the right to call off the project anytime during the process without assigning any reason, but the Administrative Department may call off the project before entering into an agreement with the project proponent or the successful bidder, as the case may be.
7. The Project Proponent is technically and financially competent to handle the project implementation for which the proposal has been submitted.
8. The Project Proponent understands and agrees that if the project proponent fails to submit the Detailed Proposal/DPR within the time given by the Administrative Department for the same, then, the Administrative Department may at its discretion exercise the option to develop the project on its own, through its agencies or through any third party, without the Project Proponent having any claims, whatsoever.
9. The Project Proponent agrees to abide by the Rajasthan Transparency in Public Procurement Act, 2012 and Rajasthan Transparency in Public Procurement Rules, 2013.
10. That the above statements are true to the best of my knowledge and belief.
Dated:(Signature, Name and Designation of Authorised Representative of Project Proponent)[Form No. 3] [Added by Rajasthan Notification No. G.S.R. 37, dated 5.6.2015 (w.e.f. 24.1.2013).][See Rule 79-D]Details of Proposal by Project ProponentName of the Project Proponent:Name of the Project:| S. No. | Description | Yes / No (wherever applicable) | Particulars | Reference/Form |
| 1. | General Information on the Project: | |||
| 1.1 | Define/Brief the Project Proposal | |||
| 1.2 | Explain the uniqueness of the project i.e. thereasons for its being unique. | |||
| 1.3 | Characteristics of the Project | |||
| 1.4 | Cost of the Project and Other Details | |||
| 1.5 | State whether the letter has been submitted bythe project proponent adhering the conditions of the SwissChallenge Method | |||
| 2. | Assessment of Need of the project | |||
| 2.1 | Nature of intended use | |||
| 2.2 | Justification of need | |||
| 3. | Details on technology (applicable in case ofnew technology) | |||
| 3.1 | Details of technology used for the project | |||
| 3.2 | Is the technology proprietary? | |||
| 3.3 | (a) Why should Government go for this technologyonly? | |||
| (b) What if sourcing of another technology hasto be made in future during the life of the project for anyreason? | ||||
| 4. | Need for Government Support | |||
| 4.1 | State the type of Government support required, ifany, and why? | |||
| 4.2 | Will the proponent be able to raise necessaryfunds & equity to undertake the project? (State how) | |||
| 5. | Eligibility of the proponent to undertake theproject | |||
| 5.1 | Is proponent planning to undertake the projecton its own or through a consortium to meet the technical,financial and technological needs? Please Elaborate. | - | ||
| 6. | Prefeasibility report | |||
| 6.1 | Has the proponent conducted prefeasibility /feasibility DPR (state the position/ information)? | |||
| 6.2 | State whether the preliminary financialviability of the project has been done. | |||
| 6.3 | State whether the proponent shall undertake allthe studies which are required for development of the project totake it to the bidding phase within the timeframe specified inthese rules. | |||
| 7. | Project Structure & Output | |||
| 7.1 | Whether the model (BOOT, BOT etc.), concessionperiod, if any, been mentioned in the report? | |||
| 7.2 | Service/ Output levels (Specify if applicable) | |||
| 8. | Project Financials | |||
| 8.1 | User Fee, Tariff/fares(Specify) and theirvariation with time | |||
| 8.2 | Provide all IRR details and provide NPV of theproject from income from operations and other forms. | |||
| 9. | Clearance / Approvals | |||
| 9.1 | State whether the environmental assessment isrequired for the project | |||
| 9.2 | State whether the project proponent hasmentioned all related approvals (Statutory or otherwise) requiredfor the project. | |||
| 10. | Qualifications of project proponent | |||
| 10.1 | State whether the proponent has the technicalcompetence for undertaking the Project? If yes, how? | |||
| 10.2 | State whether the proponent has the financialcompetence for undertaking the Project? If yes, how? | |||
| 10.3 | Any other, if any | |||
| 11. | Any other | |||
| 11.1 | Any other item/observation which the proponentfeels additionally relevant to mention. | |||
| 11.2 | Whether the project proponent agrees to comeunder the regulatory authority as and when formed by the Govt, orthrough law? | |||
| 11.3 | Is this a conditional proposal? Please specify. |
2. Appropriate response to queries in Yes/ No, where applicable, has been given and details, as required, have been elaborated under 'Particulars' column.
3. It is agreed that the above form could be modified or additional information sought by the Administrative' Department concerned at any time in future.
4. The above Form is provided in signed hard copy and also in soft copy.
Signature of the Head of the Organization / Agency (Project Proponent) with Stamp and Date[Form No. 4] [Added by Rajasthan Notification No. G.S.R. 37, dated 5.6.2015 (w.e.f. 24.1.2013).][See Rule 79D]Content of pre-feasibility report1. Introduction
2. Sector Profile
3. Market Assessment
4. Project Concept
5. Statutory & Legal Framework
6. Environmental & Social Impacts
7. Project Financials
8. Operation Framework
9. Way Ahead
10. Any other approvals (statutory or otherwise) required from any authority
11. Form:
1. Executive Summary
2. Project profile
3. Proposed business profile
4. Market analysis
5. Establishing the need of the project
6. Policy support and activities
7. Land and site analysis
8. Proposed master plan, technical specifications & project cost estimates
9. Project means of finance & financial appraisal
10. Identification of risks
11. Economic benefits of the project
12. Environment assessment (if applicable)
13. Project structure and implementation schedule
14. Project operation and maintenance Operation and maintenance framework
15. Any other approvals (statutory or otherwise) required to be taken from Government of Rajasthan / Government of India/any other authority.
16. List of Forms (To be submitted as applicable)
| S.No. | Item | Response | Ref. /Form |
| 1. | General | ||
| 1.1 Name of the Project | |||
| 1.2 Type of PPP (BOT, BOOT, BOLT, OMT etc.), ifapplicable | |||
| 1.3 Location (State/District/Town) | |||
| 1.4 Administrative Department concerned | |||
| 1.5 Name of the Implementing Agency/Proponent | |||
| 1.6 Concession Period | .... | ||
| 2. | Project Description | ||
| 2.1 Brief description of the project | |||
| 2.2 Justification for the project (Need) | |||
| 2.3 Possible alternatives, if any | |||
| 2.4 Estimated capital costs with break-up undermajor heads of expenditure. Also indicate the basis of costestimation. | |||
| 2.5 Investment phasing | |||
| 2.6 Project Implementation Schedule (PIS) | |||
| 3. | Financing Arrangements | ||
| 3.1 Sources of financing (equity, debt etc.) | |||
| 3.2 Indicate the revenue streams of the Project(Annual flows over project life). Also indicate the underlyingassumptions. | |||
| 3.3 Indicate the NPV of revenue streams | |||
| 3.4 Tariff/ user charges? Please specify indetail. | |||
| 3.5 Have any FIs been approached? If yes, theirresponse may be indicated | |||
| 3.6 Value for Money Analysis | |||
| 4. | Internal Rate of return (IRR) | ||
| 4.1 Economic IRR (if computed) | |||
| 4.2 Financial IRR, indicating variousassumptions (attach separate sheet if necessary) | |||
| 5. | Clearances | ||
| 5.1 Status of environmental clearances | |||
| 5.2 Clearances/approvals (statutory orotherwise) required from Government of India, State Governmentand other authorities/local bodies | |||
| 5.3 Other support required from the StateGovernment | |||
| 6. | Support from Government of Rajasthan | ||
| 6.1 Viability Gap Funding, if required | |||
| 6.2 Government of Rajasthan guarantees beingsought, if any | |||
| 7. | Concession Agreement | ||
| 7.1 Is the Concession Agreement based on MCA? Ifyes, indicate the variations, if any, in a detailed note (to beattached) | |||
| 7.2 Details of Concession Agreement (To beattached along with the submission) | |||
| 8. | Others | ||
| 8.1 Remarks, if any |
1. While preparing this format, the placement of relevant references / Form in the detailed proposal has been mentioned as above.
2. It is agreed that the above format could be modified or additional information sought by the Administrative Department concerned at any time in future.
3. The above Form is provided in signed hard copy and separately in soft copy also.
Signature of the Head of the Organization (Project Proponent) with date and stamp[Form No. 7] [Added by Rajasthan Notification No. G.S.R. 37, dated 5.6.2015 (w.e.f. 24.1.2013).][See Rule 79E]Project Financial Summary| S.No. | Item | Response |
| 1 | General | |
| 1.1 Name of the Project | ||
| 1.2 Type of PPP (BOT, BOOT, BOLT, OMT etc.), ifapplicable | ||
| 1.3 Capacity of the Project | ||
| 1.4 Concession Period | ||
| 2. | Project cost | |
| 2.1 Land cost | ||
| 2.2 Building cost | ||
| 2.3 Plant & Machinery cost | ||
| 2.4 Operation & maintenance cost | ||
| 2.5 Other Costs if any | ||
| 3. | Financing Arrangements | |
| 3.1 Financing Structure (% of equity and debt) | ||
| 3.2 Interest on debt (Assumed) | ||
| 3.3 Is any financial support from GoR required? | ||
| 4. | Revenue streams for each Concession Year | |
| 4.1 Revenue from Tariff. | ||
| 4.2 Revenue from Advertising | ||
| 4.3 Other Revenue Streams | ||
| 4.4Indicate the NPV of revenue streams with 12%discounting | ||
| 5. | IRR | |
| 5.1 Economic IRR (if computed) | ||
| 5.2 Equity IRR | ||
| 5.3 Project IRR | ||
| 6. | Other remarks, if any |
| S. No. | Documents to be Submitted | Applicable (Y/N) | Submitted Hard Copy (Y/N) | Submitted Soft Copy (Y/N) |
| 1. | Covering Letter from Head of the Organization | |||
| 2. | Detailed Project Report | |||
| 3. | Project Information Memorandum | |||
| 4. | Earnest Deposit & Bid Value | |||
| 5. | Draft Concession Agreement and if any changeshave been undertaken with respect to the MCA | |||
| 6. | Documents relating to any issues on variousclearances/ Land Acquisition | |||
| 7. | Details of any Policy Changes Required forimplementation (if any) | |||
| 8. | Project implementation schedule | |||
| 9. | Details for any other support required duringimplementation |