Section 5(4)(a) in Rajasthan Electricity Regulatory Commission (tariff for Captive Power Plants) Regulations, 2007
(a)Variable Charge (VC) in Rs/ kWh,shall be the sum of the cost of normative quantities of primary and secondary fuel for delivering ex-bus one kWh of electricity in Rs/kWh and shall be computed as under: