State of Karnataka - Section

Section 15 in Karnataka Town and Country Planning Act, 1961

15. Permission for development of building or land.

(1)On receipt of the application for permission under section 14, the Planning Authority shall furnish to the applicant a written acknowledgment of its receipt and after such inquiry as may be necessary either grant or refuse a commencement certificate:Provided that such certificate may be granted subject to such general or special conditions as the State Government may, by order made in this behalf, direct.
(2)If the Planning Authority does not communicate its decision to the applicant within three months from the date of such acknowledgment, such certificate shall be deemed to have been granted to the applicant.[Provided that the land use, change in land use or the development for which permission was sought for is in conformity with the outline development plan and the regulation finally approved under sub-section (3) of section 13.] [Inserted by Act 17 of 1991 w.e.f. 19.04.1991]
(3)Subject to the provisions of section 16, no compensation shall be payable for the refusal of or the insertion or imposition of conditions in the commencement certificate.
(4)If any person does any work on, or makes any use of, any property in contravention of section 14 or of sub-section (1) of this section, the Planning Authority may direct such person by notice in writing, to stop any such work in progress or discontinue any such use; and may, after making an inquiry in the prescribed manner, remove or pull down any such work and restore the land to its original condition or, as the case may be, take any measure to stop such use.
(5)Any expenses incurred by the Planning Authority under sub-section
(4)shall be a sum due to such Authority under this Act from the person in default or from the owner of the land.Explanation. - The power to grant necessary permission under this section for a change of user of land shall include the power to grant permission for the retention on land of any building or work constructed or carried out thereon before the date of the publication of the declaration of intention to prepare an outline development plan under sub-section (1) of section 10 or for the continuance of any use of land instituted before the said date.
(6)[ Any person aggrieved by the decision of the Planning Authority under sub-section (1) or sub-section (4) may, within thirty days from the date of such decision, appeal to such authority as may be prescribed.
(7)The prescribed authority may, after giving a reasonable opportunity of being heard to the appellant and the Planning Authority, pass such orders as it deems fit, as far as may be, within four months from the date of receipt of the appeal.] [Sub-sections (6) and (7) Inserted by Act 17 of 1991 w.e.f. 19.4.1991]