Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 31]

Supreme Court of India

Bharat Barrel And Drum Mfg. Co.Private ... vs Govind Gopal Waghmare And Another on 24 March, 1960

Equivalent citations: 1960 AIR 873, 1960 SCR (3) 378, AIR 1960 SUPREME COURT 873, 1960 3 SCR 378, 1960 -61 19 FJR 247, 1960 2 LABLJ 241, 1960 SCJ 1230

Author: K.N. Wanchoo

Bench: K.N. Wanchoo, P.B. Gajendragadkar, K.C. Das Gupta

           PETITIONER:
BHARAT BARREL AND DRUM MFG.  CO.PRIVATE LTD.

	Vs.

RESPONDENT:
GOVIND GOPAL WAGHMARE AND ANOTHER

DATE OF JUDGMENT:
24/03/1960

BENCH:
WANCHOO, K.N.
BENCH:
WANCHOO, K.N.
GAJENDRAGADKAR, P.B.
GUPTA, K.C. DAS

CITATION:
 1960 AIR  873		  1960 SCR  (3) 378
 CITATOR INFO :
 R	    1961 SC1191	 (3)
 R	    1963 SC1007	 (13)


ACT:
Industrial    Dispute--Full    Bench	 formula--Income-tax
Payable--Test.



HEADNOTE:
The  workmen of the appellant company claimed  four  months,
wages  including  dearness allowance as bonus for  the	year
1952,  and  retrospective operation of	the  increased	wage
scale  to be fixed by the Industrial Tribunal from March  1,
1952.	The  appellant agreed to the  increased	 wage  scale
suggested  by  the  Tribunal but wanted that  it  should  be
linked	to  some  guaranteed  production,  and	opposed	 its
operation retrospectively on the ground that there had	been
eliberate  slowing down of production by the workmen in	 the
previous  years.   The Tribunal found that  there  was	some
justification  in the appellant's contention that there	 was
considerable  go-slow  which  had  affected  production	 and
ordered	 that  retrospective effect should be given  to	 its
order relating to increase in wages which was passed on	 May
13,  1957,  from  June 1, 1956, and not March  1,  1952,  as
claimed by the workmen, The increased wages were not  linked
to any guaranteed production but it was made clear that	 the
workers	 would give certain reasonable production  to  which
the workmen agreed.  The Tribunal granted five months  basic
wages by way of bonus on the basis of the Full Bench formula
which  is generally applied to these matters.  On appeal  by
the Appellant-company by special leave :
Held,  that  there was no reason for interference  with	 the
order of the Tribunal fixing the date as June 1, 1956,	from
which  the increased wages should come into force  and	that
the  Tribunal had jurisdiction to award five  months'  basic
wages by way of bonus.
For  the  purpose of the Full Bench formula,  the  incometax
payable	 has  to  be  deducted on  the	figures	 worked	 out
according  to  the  formula and it is  immaterial  what	 the
actual income-tax paid is-whether more or less.



JUDGMENT:

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 93 of 1959. Appeal by special leave from the Award dated May 13, 1957, of the Industrial Tribunal, Bombay, in Reference (I.T.) No. 166 of 1955.

R. J. Kolah, S. N. Andley, J. B. Dadachanji, Rameshwar Nath and P. L. Vohra, for the appellants.

K. B. Chaudhury and Janardan Sharma, for the respondents Nos. 1 and 2.

379

1960. March 24. The Judgment of the Court was delivered by WANCHOO, J.-This appeal by special leave raises two questions, namely, (i) bonus for the year 1952 and (ii) retrospective operation of the order of the Industrial Tribunal relating to increase in wages. The appellant is a company manufacturing barrels and drums at Bombay. There was a dispute between the appellant and its workmen about a number of matters, which was referred to the tribunal by the Government of Bombay on November 17, 1955. In respect of the two matters which are now raised in appeal the workmen claimed (i) four months wages including dearness allowance as bonus for the year 1952 and (ii) retrospective operation of the wage-scale to be fixed by the tribunal from March 1, 1952.

So far as the increase in wages, is concerned, the appellant agreed to the scale suggested by the tribunal but it opposed the grant of the increased scale retrospectively and also wanted that the increased wages should be linked to some guaranteed production. The reason for this was that the appellant felt that there had been deliberate slowing down of production by the workmen in the previous years. The tribunal was of opinion that there was some justification in the appellant's contention that there had been considerable go-slow which had affected production. Taking that into account it ordered that retrospective effect should be given to its order which was passed on May 13, 1957 from June 1, 1956. As to the linking of the increased wages to a certain guaranteed production it found it difficult to lay down any norm itself; but it made it clear that the increase in wages was made by it on the basis that the workers would give a certain reasonable production and noted that the workers were agreeable to do that. It, however, recommended that immediately after the. award had been given, an expert should be appointed by agreement, if possible, to go into this question. It also said that in case it was not possible to appoint an expert by agreement it would be open to the appellant to appoint one.

380

The appellant's contention before us is that the tribunal having found some justification in its contention that there had been considerable go-slow should not have given retrospective effect at all to the order relating to the increase in wages. This matter has been considered fully by the tribunal and it came to the conclusion that increase in wages should be granted from June 1, 1956. This could hardly be called retrospective considering that the reference was made in November 1955 ; in any case the tribunal rejected the claim of the workmen for retrospective operation for the period of over four years from March 1952 to May 1956 and a good deal of go-slow was practised during this period. In the circumstances we see no reason for interference with the order of the tribunal fixing the date as June 1, 1956, from which the increased wages should come into force.

This brings us to the next question relating to bonus. The tribunal has awarded five months' basic wages by way of bonus. The first contention in this connection is that the workmen had only claimed four months' basic wages and the tribunal could not have awarded anything more than what the workmen claimed. This in our opinion is incorrect. The workmen had claimed four months' wages including dearness allowance as bonus. Five months' basic wages which the tribunal has allowed are admittedly less than the claim put forward (namely, four months' wages including dearness allowance). In the circumstances the tribunal certainly had jurisdiction to award what it has awarded to the workmen. The next question is whether the tribunal was justified in awarding as much as five months' basic wages on the basis of the Full Bench formula, which is generally applied to these matters. The gross profit found by the tribunal is not challenged, namely, Rs. 5.05 lacs. The tribunal has then allowed Rs. 1.36 lacs as depreciation, leaving a balance of Rs. 3.69, lacs. Deducting income-tax from this at seven annas in a rupee (i.e. Rs. 1.61 lacs), we are left with a balance of Rs. 2.08 lacs. Six per cent. per annum interest on the paid-up capital along with four per cent. interest on the working capital comes to Rs. 16,000, leaving an available 381 surplus of Rs. 1.92 lacs. Out of this, the tribunal has allowed five months' basic wages as bonus which according to its calculations comes to Rs. 91,000, leaving Rs. 1.01 lacs. There will be a rebate of Rs. 40,000 on this sum, leaving a total of Rs. 1.41 lacs with the appellant. On these figures, the bonus awarded by the tribunal cannot be interfered with.

The appellant, however, draws our attention to two circumstances in this connection. In the first place it urges that the tribunal has not taken into account anything for rehabilitation. But it may be mentioned that the appellant had proved no rehabilitation amount as such. What it had done was to appropriate Rs. 3.16 lacs towards depreciation, which of course was not the proper amount of notional normal depreciation, which is allowable under the formula. Our attention is drawn, however, to the figures filed by the workmen in Ex. U-4 in which Rs. 40,000 has been allowed towards rehabilitation. Even accepting this concession by the workmen and deducting it from the figures given by us above, the appellant would still be left with Rs. 1.01 lacs after paying five months' basic wages as bonus. There is thus no reason to interfere with the award of bonus on this ground.

Lastly it is urged that according to the income-tax assessment which was actually made in this case sometime after the order of the tribunal, the appellant has been assessed to income-tax amounting to Rs. 2.35 lacs. The appellant claims that it should be allowed this entire amount and not the notional figure calculated by us, namely, Rs. 1.61 lacs as income-tax. We are of opinion that for the purpose of the Full Bench formula, the income-tax payable has to be deducted on the figures worked out according to the formula and it is immaterial what the actual income -tax paid is-whether more or less. In this particular case, the income-tax appears to be more because certain items which were challenged by the workmen but were allowed as proper expense by the tribunal have apparently not been allowed as proper expense by the income-tax department. The industrial tribunal, however, is not concerned directly with what the income 49 382 tax authorities assess as actual income-tax in a particular year; it is concerned with working out the Full Bench formula in accordance with its notional calculations and this is what has been done in this case. There is no ground therefore for interference-with the award of bonus for this reason either.

We therefore dismiss the appeal, but in the circumstances pass no order as to costs.

Appeal dismissed.