Union of India - Subsection

Section 8(5) in Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010

(5)[ Where the Approved Withdrawal or Approved Injection in case of a DIC is not materializing either partly or fully for any reason whatsoever, the concerned DIC shall be obliged to pay the transmission charges allocated under these regulations:Provided that in case the commissioning of a generating station or unit thereof is delayed, the generator shall be liable to pay Withdrawal Charges corresponding to its Long term Access from the date the Long Term Access granted by CTU becomes effective. The Withdrawal Charges shall be at the average withdrawal rate of the target region:Provided further that where the operationalization of LTA is contingent upon commissioning of several transmission lines or elements and only some of the transmission lines or elements have been declared commercial, the generator shall pay the transmission charges for LTA operationalised corresponding to the transmission system commissioned:Provided also that where the construction of dedicated transmission line has been taken up by the CTU or the transmission licensee, the transmission charges for such dedicated transmission line shall be payable by the generator as provided in the Regulation 8 (8) of the Connectivity Regulations:[Provided also that a generating station drawing start-up power or injecting infirm power before commencement of LTA shall be liable to pay the withdrawal or injection charges corresponding to the actual injection of infirm power or withdrawal start-up power during a month (concerned month) and the amount received on account of such payments shall be reimbursed to the DICs in the month following the month of billing, in proportion to the billing of the DICs during the concerned month.] [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (15.6.2010).]Provided also that CTU shall maintain a separate account for the above amount received in a quarter and deduct the same from the transmission charges of ISTS considered in PoC calculation for the next application period.]