[Cites 0, Cited by 0] [Section 6] [Entire Act]

State of Madhya Pradesh - Subsection

Section 6(1) in MPERC (Micro-Grid Renewable Energy Generation and Supply) Regulations, 2016

(1)Technical Standards for Interconnection with the Grid shall be issued in the implementation guidelines by the State Nodal Agency in consultation with Distribution Licensee and approved by the Commission. State Nodal Agency can also follow the standards issued by the Authority for Micro-Grid projects in future.