[Cites 0, Cited by 0] [Section 35] [Entire Act]

State of Himachal Pradesh - Subsection

Section 35(3) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

(3)The normative year wise net saleable energy for the purpose of project specific tariff determination shall also be worked out on similar lines given in sub-regulations (1) and (2) but by taking into account the annual Capacity Utilisation Factor (CUF) in accordance with clause (ii) of subregulation (1) of regulation 15, the normative auxiliary consumption and transformation losses under regulation 37 and the energy losses in the project line under regulation 38.