Section 13(2)(f) in Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011
(f)any liability for works admitted by the Commission after the Cut-off Date to the extent of discharge of such liabilities by actual payments;