State of Himachal Pradesh - Act
Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011
HIMACHAL PRADESH
India
India
Himachal Pradesh Electricity Regulatory Commission (Terms and Conditions for Determination of Hydro Generation Tariff) Regulations, 2011
Rule HIMACHAL-PRADESH-ELECTRICITY-REGULATORY-COMMISSION-TERMS-AND-CONDITIONS-FOR-DETERMINATION-OF-HYDRO-GENERATION-TARIFF-REGULATIONS-2011 of 2011
- Published on 1 April 2011
- Commenced on 1 April 2011
- [This is the version of this document from 1 April 2011.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title, extent and commencement.
2. Scope and application.
3. Definitions.
- In these regulations, unless the context otherwise requires, -2. In case of purely run-of-river hydro generating station if the unit or the generating station is declared under commercial operation during lean inflows period when the water is not sufficient for such demonstration, it shall be mandatory for such hydro generating station or unit to demonstrate peaking capability equivalent to the installed capacity as and when sufficient inflow is available.
4. General Approach.
5. Multi Year Tariff (MYT) Framework.
6. Determination of Baseline.
7. Capital Investment.
- Subject to the provisions of the Act, and the rules and policies made thereunder, the Commission shall approve the capital investment plan of a generating company for the control period commensurate with generation capacity growth. The investment plan shall also include a capitalisation schedule and financing plan for the planned investment. Adjustment for the actual capital investment vis-a-vis approved capital investment shall be done at the end of the control period.8. Performance Targets.
9. True Up.
9A. [ Carrying Cost. [Inserted by Notification No. HPERC-F(1)-2/2018, dated 22.11.2018 (w.e.f. 1.4.2011).]
- The generating company, for the approved true-up of any year over and above that approved in the Tariff Order for that year, shall be entitled to a carrying cost at one (1) Year weighted average State Bank of India (SBI) MCLR/any replacement thereof as notified by RBI for the time being in effect applicable for one (1) Year period of the relevant Year plus 300 basis points and for any true-up resulting in less than that approved in the Tariff Order for that year, the carrying cost shall be recovered at the same rate.]10. [ Refund of excess amount. [Substituted by Notification No. HPERC-F(1)-2/2018, dated 22.11.2018 (w.e.f. 1.4.2011).]
- If a generating company recovers the charges exceeding the tariff determined by the Commission, the excess amount shall be refunded to beneficiaries, who have paid such excess charges, along with interest equivalent to the one (1) Year State Bank of India (SBI) MCLR/any replacement thereof as notified by RBI for the time being in effect applicable for one (1) Year period, as may be applicable as on 1st April of the Financial Year plus 300 basis points, without prejudice to any other liability to which such generating company may be subject:Provided that such interest payable to any party shall not be allowed to be recovered through the Aggregate Revenue Requirement of the generating company:Provided further that the generating company shall maintain separate details of such interest paid or payable by it, and shall submit them to the Commission along with its petition.]10A. [ Preparation of Accounting Manual and Regulatory Accounts. [Inserted by Notification No. HPERC-F(1)-2/2018, dated 22.11.2018 (w.e.f. 1.4.2011).]
- The Generating Company shall prepare Accounting Manual and Regulatory Accounts as per the Himachal Pradesh Electricity Regulatory Commission (Reporting System on Power Regulatory Accounting) Regulations, 2014. The Utility shall submit the Regulatory Audited Accounts every year within seven months of the end of the Financial Accounting Year to the Commission.10B. Segregation of Accounts.
- The generating company shall maintain separate accounts for each of its hydro power plants:Provided that the generating company shall follow a reasonable basis for allocation of all joint and common costs between the power plants and shall submit the Accounting Statements, as approved by its board of directors, to the Commission alongwith its application for determination of tariff.10C. Consumer Contribution, Deposit Work, Grant and Capital Subsidy.
11. Capital cost of project.
12. Initial Spares.
- For hydro generating stations, initial spares shall be capitalised as a percentage of the original project cost, subject to the ceiling norm of 1.5%:Provided that the Commission, may for sufficient reasons to be recorded in writing, after exercising due diligence and applying prudency check, deviate from the above ceiling norm.13. Additional Capitalisation.
14. Renovation and Modernisation.
15. Sale of Infirm Power.
- Supply of infirm power shall be accounted as Unscheduled Interchange (UI) and paid for from the regional or State UI pool account at the applicable frequency-linked UI rate:Provided that any revenue earned by the generating company from sale of infirm power shall be applied for reduction in capital cost.16. Debt-Equity Ratio.
17. Interest and Finance Charges.
18. Working Capital.
- The Commission shall calculate the working capital requirement for hydro electric power stations containing the following components: -19. [ Interest on Working Capital. [Substituted by Notification No. HPERC-F(1)-2/2018, dated 22.11.2018 (w.e.f. 1.4.2011).]
- Rate of interest on working capital to be computed as provided hereinafter in these regulations shall be on normative basis and shall be equal one (1) Year State Bank of India (SBI) MCLR / any replacement thereof as notified by RBI for the time being in effect applicable for one (1) Year period, as may be applicable as on 1st April of the Financial Year in which the Petition is filed plus 300 basis points. The interest on working capital shall be payable on normative basis notwithstanding that the generating company has not taken working capital loan from any outside agency or has exceeded the working capital loan based on the normative figures.]20. Depreciation.
21. Return on Equity.
22. Operation and Maintenance (O&M) Expenses.
23. Operational Norms.
| Surface hydro electric power generating station | With rotating exciters mounted on the generatorshaft | 0.7% |
| With static excitation system | 1% | |
| Underground hydro electric power generatingstation | With rotating exciters mounted on the generatorshaft | 0.9% |
| With static excitation system | 1.2% |
24. Computation of Tariff.
- The tariff for supply of electricity from a hydro generating station shall comprise capacity charge and energy charge to be derived in the manner specified in regulation 26, for recovery of annual fixed cost (consisting of the components referred to in regulation 25) through the two charges.25. Annual Fixed Cost.
- The annual fixed cost (AFC) of a generating station shall consist of the following components:-26. Computation of Capacity Charge and Energy Charge.
27. Unscheduled Interchange (UI) Charges.
- The generating station may be entitled to receive or shall be required to bear, as the case may be, the charges for deviations between energy sent-out corresponding to scheduled generation and actual energy sent-out shall be accounted for through Unscheduled Interchange (UI) charges, as per the rate approved by the Appropriate Commission.28. Billing and payment of charges.
- Bills shall be raised for capacity charge and energy charge on monthly basis by the generating company in accordance with these regulations, and payments shall be made by the beneficiaries directly to the generating company.Note. - FEHS = Free energy for State, in percent and shall be taken at actual subject to maximum of 13% in accordance with the National Hydro Policy29. Late Payment Surcharge.
- In case the payment of any bill for charges payable under these regulations is delayed by a beneficiary beyond a period of 60 days from the date of billing a late payment surcharge at the rate of 1.25% per month shall be levied by the generating company.30. Rebate.
- For payment of bills of the generating company through a letter of credit on presentation, a rebate of 2% shall be allowed. If the payment is made by any other mode but within a period of one month of presentation of bills by the generating company, a rebate of 1% shall be allowed.31. Scheduling.
- The methodology for scheduling and dispatch for the generating station shall be as specified in the Himachal Pradesh Electricity Grid Code as amended from time to time.32. Demonstration of Declared Capacity.
33. Metering and Accounting.
- For metering and accounting, the provisions of the Himachal Pradesh Electricity Grid Code, as amended from time to time, shall be applicable.34. Safety Standards.
- The generating company shall develop a safety manual and follow procedures to maintain minimum safety standards during construction, operation, etc. in line with the provisions of section 53 of the Act.Part - V Multi Year Tariff Filing Procedure35. Multi-Year Filings for the control period.
36. Beginning of the control period-business plan filings.
37. Tariff Filing.
- The applicant shall file the application for approval of generation tariff for each year of the control period consistent with the business plan, not less than 120 days before the commencement of the first year of the control period or such other date as may be directed by the Commission.38. Review at the end of the control period.
- Towards the end of the control period, the Commission shall review if the implementation of the principles laid down in these regulations has achieved their intended objectives. While doing this, the Commission shall take into account, among other things, the industry structure, sector requirements, consumer and other stakeholder expectations and the applicant's requirements at that point in time. Depending on the requirements of the sector to meet the objects of the Act, the Commission may revise the principles for the next control period.39. Disposal of Application.
40. Periodic Reviews.
41. Publication.
- The generating company shall publish the tariff approved by the Commission in the newspapers, having circulation in the area of supply, as the Commission may direct. The publication shall, besides such other things as the Commission may require, include a general description of the tariff changes.Part - VI Miscellaneous42. Sharing of Clean Development Mechanism (CDM) Benefits.
43. Tax on Income.
- In view of pre tax return on equity, tax on the income streams of the generating company shall not be recovered from the beneficiaries:Provided that the deferred tax liability, excluding Fringe Benefit Tax, for the period up to 31st March, 2011 whenever it materialises, shall be recoverable directly from the beneficiaries and the long-term customers.44. Foreign Exchange Rate Variation.
45. Recovery of cost of hedging Foreign Exchange Rate Variation.
- Recovery of cost of hedging and foreign exchange rate variation shall be made directly by the generating company from the beneficiaries without making any application before the Commission:Provided that in case of any objections by the beneficiaries to the amounts claimed on account of cost of hedging or foreign exchange rate variation, the generating company makes an appropriate application before the Commission for its decision.46. Transitory provisions.
- Notwithstanding anything to the contrary contained in these regulations -47. Issue of Orders and Practice Directions.
48. Power to remove difficulties.
- If any difficulty arises in giving effect to any of the provisions of these regulations, the Commission may, by a general or special order, not being inconsistent with the provisions of these regulations or the Act, do or undertake to do things or direct the generating company to do or undertake such things which appear to be necessary or expedient for the purpose of removing the difficulties.49. Power of relaxation.
- The Commission may, in public interest and for reasons to be recorded in writing, relax any of the provisions of these regulations.50. Interpretation.
- All issues arising in relation to the interpretation of these regulations shall be determined by the Commission and the decision of the Commission on such issues shall be final.51. Saving of Inherent Powers of the Commission.
- Nothing contained in these regulations shall limit or otherwise affect the inherent powers of the Commission from adopting a procedure, which is at variance with any of the provisions of these regulations, if the Commission, in view of the special circumstances of the matter or class of matters and for reasons to be recorded in writing, deems it necessary or expedient to depart from the procedure specified in these regulations.52. Enquiry and Investigation.
- All enquiries, investigations and adjudications under these regulations shall be done by the Commission in accordance with the provisions of the Conduct of Business Regulations.53. Repeal and Savings.
| No | Asset Particulars | Depreciation Rate (Salvage Value=10%) |
| A | Land under full ownership | 0.00% |
| B | Land under lease | |
| (a) | For investment in land | 3.34% |
| (b) | For cost of clearing the site | 3.34% |
| (c) | Land for reservoir in case of hydro generatingstation | 3.34% |
| C | Assets purchased new | |
| (a) | Plant and Machinery in generating stations | |
| (i) | Hydro-electric | 5.28% |
| (b) | Hydraulic works forming part of hydro-electricsystem including: | |
| (i) | Dams, spillways weirs, canals, reinforcedconcrete flumes & siphons | 5.28% |
| (ii) | Reinforced concrete pipelines and surge tanks,steel pipelines, sluice gates, steel surge (tanks) hydrauliccontrol valves and other hydraulic works | 5.28% |
| D | Buildings and civil engineering works of apermanent character, not mentioned above: | |
| (i) | Offices & showrooms | 3.34% |
| (ii) | Containing hydro-electric generating plant | 3.34% |
| (iii) | Temporary erection such as wooden structures | 100.00% |
| (iv) | Roads other than kutcha roads | 3.34% |
| (v) | Others | 3.34% |
| E | Transformers, transformer (kiosk) sub-stationequipment & other fixed apparatus (including plantfoundations) | |
| (i) | Transformers (including foundations) having arating of 100 kilo volt amperes and over | 5.28% |
| (ii) | Others | 5.28% |
| F | Switchgear, including cable connections | 5.28% |
| G | Lightning arrestors: | 5.28% |
| (i) | Station type | 5.28% |
| (ii) | Pole type | 5.28% |
| (iii) | Synchronous condenser | 5.28% |
| H | Batteries | 5.28% |
| No | Asset Particulars | Depreciation Rate (Salvage Value=10%) |
| (i) | Underground cable including joint boxes anddisconnected boxes | 5.28% |
| (ii) | Cable duct system | 5.28% |
| I | Overhead lines including supports: | |
| (i) | Lines on fabricated steel operating at nominalvoltages higher than 66 kV | 5.28% |
| (ii) | Lines on steel supports operating at nominalvoltages higher than 13.2 kV but not exceeding 66 kV | 5.28% |
| (iii) | Lines on steel or reinforced concrete supports | 5.28% |
| (iv) | Lines on treated wood supports | 5.28% |
| J | Meters | 5.28% |
| K | Self propelled vehicles | 9.50% |
| L | Air conditioning plants: | |
| (i) | Static | 5.28% |
| (ii) | Portable | 9.50% |
| M(i) | Office furniture and fittings | 6.33% |
| (ii) | Office equipments | 6.33% |
| (iii) | Internal wirings including fittings andapparatus | 6.33% |
| (iv) | Street Light fittings | 5.28% |
| N | Apparatus let on hire: | |
| (i) | Other than motors | 9.50% |
| (ii) | Motors | 6.33% |
| O | Communication equipment | |
| (i) | Radio and higher frequency carrier systems | 6.33% |
| (ii) | Telephone lines and telephones | 6.33% |
| P | I.T Equipment | 15.00% |
| Q | Any other assets not covered above | 5.28% |