Section 7(1)(q) in Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010
(q)[ The recovery of the Yearly Transmission Charges (YTC) of the ISTS network shall be based on the Hybrid Methodology (PoC charge), Reliability Support Charge and HVDC Charge. Ten percent (10%) of the Yearly Transmission Charges shall be recovered through Reliability Support Charge Sharing methodology. The Commission may review the weightage accorded to Reliability Support Charge whenever deemed necessary. The Reliability support charge rates shall be determined separately and shall not be mixed with zonal PoC rates. The Reliability Support Charge shall be payable by the DICs in proportion to their Approved Withdrawal. In case of Injection DIC shaving Long Term Access to target region, Reliability Support Charges shall also be payable in proportion to their Approved Injection.] [Substituted by Notification No. L-1/44/2010-CERC, dated 1.4.2015 (w.e.f. 15.6.2010).]