Section 12(4) in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

(4)The bank guarantee of Rs. 10,000 /-(ten thousand) per MW shall be kept valid and subsisting till the execution of the long-term access agreement, in the case when augmentation of transmission system is required, and till operationalization of long-term access when augmentation of transmission system is not required.