Union of India - Act
Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009
UNION OF INDIA
India
India
Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009
Rule CENTRAL-ELECTRICITY-REGULATORY-COMMISSION-GRANT-OF-CONNECTIVITY-LONG-TERM-ACCESS-AND-MEDIUM-TERM-OPEN-ACCESS-IN-INTER-STATE-TRANSMISSION-AND-RELATED-MATTERS-REGULATIONS-2009 of 2009
- Published on 7 July 2009
- Commenced on 7 July 2009
- [This is the version of this document from 7 July 2009.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short Title and Commencement.
2. Definitions.
3. Scope.
- These regulations, after they come into force, shall apply to the giant of connectivity, long-term access and medium-term open access, in respect of inter-State transmission system:Provided that a generating station, including captive generating plant or a bulk consumer, seeking connectivity to the inter-State transmission system cannot apply for long-term access or medium-term open access without applying for connectivity:Provided further that a person may apply for connectivity and long-term access or medium-term open access simultaneously.4. Nodal Agency.
- The nodal agency for giant of connectivity, long-term access and medium-term open access to the inter-State transmission system shall be the Central Transmission Utility.5. Filing of Application.
- Applications for giant of connectivity or long-term access or medium-term open access shall be made to the nodal agency:[Provided that an application for connectivity is not required to be made by any transmission licensee;] [Substituted by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]Provided, however, that an inter-State transmission licensee other than Central Transmission Utility, nevertheless, shall sign a connection agreement with the Central Transmission Utility, as provided for in Clause (5) of regulation 8 of these Regulations.5A. [ Processing of Application. [Added by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]
6. Application fee.
- The application referred to in regulation 5 shall be accompanied by a non-refundable application fee specified hereunder, payable in the name and in the manner to be laid down by the Central Transmission Utility in the detailed procedure: -| S. No. | Quantum of Power to be injected/off takeninto/ from ISTS | Application fee (Rs. in lakh) | ||
| For Connectivity | Long-term access | Medium-term open access | ||
| 1. | Up to 100 MW | 2 | 2 | 1 |
| 1 | More than 100 MW and up to 500 MW | 3 | 3 | 2 |
| 2 | More than 500 MW and up to 1000 MW | 6 | 6 | 3 |
| 3 | More than 1000 MW | 9 | 9 | 4 |
7. Timeframe for processing of application.
- The application shall be processed by the nodal agency within the time limits specified hereunder: -| Nature of Application | Time limit for processing beginning the last dayof the month in which application was received by the nodalagency |
| Connectivity | 60 days |
| Long-term access | 120 days whereaugmentation of transmission system is not required180 days, where augmentation of transmissionsystem is required |
| Medium-term open access | 40 days |
8. Grant of Connectivity.
8A. [ Transfer of Connectivity and LTA. [Added by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]
- A person shall not transfer, assign or pledge its connectivity or LTA either in full or parts and the associated rights and obligations to any other person:Provided that the above provision shall not be applicable to applicants defined under Regulation 2(1)(b)(i)(g):Provided further that 100% subsidiary companies shall be allowed to transfer their connectivity and LTA to the parent company and vice versa one year after achieving commercial operation of Renewable Energy generating station(s):Provided further that transfer of Connectivity and LTA from the parent company to more than one 100% subsidiary shall be permitted one year after the commercial operation of the generating station of the last subsidiary and subject to minimum capacity as per Regulation 2(1)(b):Provided also that till such Connectivity and LTA are transferred, the concerned subsidiary company(ies) shall be allowed to utilize the Connectivity and LTA granted to the parent company and vice versa.]Chapter-4 Long-Term and Medium-Term Open Access9. Criteria for granting long-term access or medium-term open access.
10. Relative priority.
11. Interface Meters.
12. Application for long-term access.
13. System Studies by the Nodal Agency.
14. Communication of Estimate of Transmission Charges, etc.
- While granting long-term access, the nodal agency shall communicate to the applicant, the date from which long-term access shall be granted and an estimate of the transmission charges likely to be payable based 011 the prevailing costs, prices and methodology of sharing of transmission charges specified by the Commission.15. Execution of Long-term Access Agreement.
- [(1) The applicant shall sign an agreement for long-term access with the Central Transmission Utility in case long-term access is granted by the Central Transmission Utility, in accordance with the provision as may be made in the detailed procedure.15A. [ Intimation regarding termination of Power Purchase Agreement. [Added vide Second Amendment Regulations, 2012 w.e.f. 22.03.2012.]
16. Information to RLDC and SLDC.
- Immediately after giant of long-term access, the nodal agency shall inform the Regional Load Despatch Centres and the State Load Despatch Centres concerned so that they can consider the same while processing requests for giant of short-term open access, received under Central Electricity Regulatory Commission (Open Access in inter-State transmission) Regulations, 2008 as amended from time to time.16A. [ [Added vide Second Amendment Regulations, 2012 w.e.f. 22.03.2012.]
On receiving the intimation regarding termination of Power Purchase Agreement, or surrender of long term access in accordance with the provisions of Regulation 15 A of these regulations and after considering the applications for long-term access and medium-term open access, if any, as mentioned therein, the nodal agency shall inform the Regional Load Despatch Centre and State Despatch Centre concerned to consider the remaining capacity for processing the request for short term open access in accordance with the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2008, as amended from time to time, till long term access or medium term open access is granted to some other applicant.]17. Renewal of Term for Long-term access.
- On the expiry of the period of long-term access, the long-term access shall stand extended on a written request provided by the long-term customer in this regard to the Central Transmission Utility mentioning the period for extension that is required:Provided that such a written request shall be submitted by the long-term customer to the Central Transmission Utility at least six months prior to the date of expiry of the long-term access;Provided further that in case no written request is received from the long-term customer within the timeline specified above, the said long-term access shall stand withdrawn.18. Relinquishment of access rights.
19. Application for Medium-term Open Access.
20. System Studies by the Nodal Agency.
- On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in inter-State transmission system to be used, including State Transmission Utility, if the State network is likely to be used, process the application and carry out the necessary system studies as expeditiously as possible so as to ensure that the decision to grant or refuse medium-term open access is made within the timeframe specified in regulation 7:Provided that in case the nodal agency faces any difficulty in the process of consultation or coordination, it may approach the Commission for appropriate directions.21. Grant of Medium-term Open Access.
22. Execution of Dedicated Transmission Line.
- Medium-term customer may arrange for execution of the dedicated transmission line at its own risk and cost before the start date of the medium-term open access.23. No overriding preference.
- On the expiry of period of the medium-term open access, the medium-term customer shall not be entitled to any overriding preference for renewal of the term.24. Exit option for medium-term customers.
- A medium-term customer may relinquish rights, frilly or partly, by giving at least 30 days prior notice to the nodal agency:Provided that the medium-term customer relinquishing its rights shall pay applicable transmission charges for the period of relinquishment or 30 days whichever is lesser.Chapter - 7 Conditions of Long-Term Access and Medium-Term Open Access25. Curtailment.
26. Transmission Charges.
- The transmission charges for use of the inter-State Transmission system shall be recovered from the long-term customers and the medium-term customers in accordance with terms and conditions of tariff specified by the Commission from time to time:Provided that if the State network is also being used in the access as a part of interstate Transmission system for the conveyance of electricity across the territory of an intervening State as well as conveyance within the State which is incidental to such interstate Transmission of electricity, recovery of charges for such State network and terms and conditions thereof shall be in accordance with the regulation as may be specified by the Commission under Section 36 of the Act for intervening transmission facilities, if such charges and terms and conditions cannot be mutually agreed upon by the licensees;Provided that any disagreement on transmission charges for such State network as specified above, shall not be the sole reason for denying access and either party may approach the Commission for determination of transmission charges for such State network.27. Detailed Procedure.
28. Fees and charges for the Regional Load Despatch Centre and the State Load Despatch Centre.
29. [ [Deleted by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]
***]| 29. Payment of transmission charges and Fees and Charges for the Regional Load Despatch Centre.- (1) The transmission charges in respect of the long-term customer and medium-term customer shall be payable directly to the transmission licensee:Provided that the Central Transmission Utility may be designated by the Commission as the agency for the purpose of collecting and disbursing the transmission charges for inter-State transmission system;Provided further that when the Central Transmission Utility is so designated as the agency as aforesaid, the transmission charges shall be paid to it;Provided also that the Central Transmission Utility shall enter into agreements with the long-term customers and medium-term customers for collection of transmission charges and with the transmission licensees whose inter-State transmission system is being used, for disbursement of transmission charges as received, pro rata to the transmission charges payable to the transmission licensees and to the Central Transmission Utility;Provided also that the Central Transmission Utility shall be entitled to reimbursement of reasonable costs incurred by it in collecting the transmission charges of the other transmission licensees, as approved by the Commission.(2) The fees and charges for Regional Load Despatch Centres (including the charges for Unified Load Despatch Scheme) and State Load Despatch Centres shall be payable by the long-term customer and medium-term customer directly to the Regional Load Despatch Centre or the State Load Despatch Centre concerned. |